630 N NIMES ROAD 90077
Certificate Information: 630 N NIMES ROAD 90077
- Application / Permit
- 20047-30000-00629
- Plan Check / Job No.
- B20WL01999
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW SWIMMING POOL AND SPA PER ENGINEERING
- Permit Issued
- Issued on 9/4/2020
- Issuing Office
- Current Status
- Issued on 9/4/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2020 | SERGIO SILVA |
| Corrections Issued | 6/8/2020 | SERGIO SILVA |
| Quality Review Completed | 6/19/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/16/2020 | SERGIO SILVA |
| Plan Check Approved | 7/30/2020 | SERGIO SILVA |
| Issued | 9/4/2020 | APPLICANT |
| Building Plans Picked Up | 9/10/2020 | APPLICANT |
Permit Application Clearance Information
| Haul Route | Cleared | 7/16/2020 | SERGIO SILVA |
| Miscellaneous | Cleared | 7/16/2020 | SERGIO SILVA |
| Miscellaneous | Cleared | 7/16/2020 | SERGIO SILVA |
| ZA Case | Cleared | 7/20/2020 | LOUIS ORTEGA |
| Grading Pre-Inspection | Cleared | 7/30/2020 | SERGIO SILVA |
Contact Information
| Architect | , ; Lic. No.: C34653 | , |
| Contractor | Scg Development Group Inc; Lic. No.: 1016344-B | 9255 SUNSET BLVD STE 1000 WEST HOLLYWOOD, CA 90069 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: C58475 | 24702 NARBONNE AVE LOMITA, CA 90717 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 2/11/2021 | Approved | ANTHONY MCDOWALL |
| Pre-Gunite | 2/23/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Gunite | 2/26/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Grounding or Bonding | 3/3/2021 | Partial Approval | CHRISTOPHER WILSON |
| Pre-Gunite | 3/3/2021 | Approved | CHRISTOPHER WILSON |
| Rough-Electrical | 3/3/2021 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 4/29/2021 | Conditional Approval | CHRISTOPHER WILSON |
| Enclosure/Fence | 3/7/2025 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Enclosure/Fence | 3/25/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Pre-Inspection | 3/25/2025 | Corrections Issued | CHRISTOPHER WILSON |
| Enclosure/Fence | 3/28/2025 | Approved | CHRISTOPHER WILSON |
| Final | 3/28/2025 | Corrections Issued | CHRISTOPHER WILSON |