9577 W LIME ORCHARD ROAD 90210

Certificate Information: 9577 W LIME ORCHARD ROAD 90210

Application / Permit
20047-30000-00565
Plan Check / Job No.
B20WL01840
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) 20'X 10' POOL & 8'X 5' SPA PER ( LA CITY STD PLAN # 265 / ENGINEERED DESIGN).
Permit Issued
Issued on 11/16/2020
Issuing Office
Current Status
CofO Issued on 7/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/24/2020 APPLICANT
Assigned to Plan Check Engineer 4/30/2020 PARISA ZAHABI
Corrections Issued 4/30/2020 PARISA ZAHABI
Applicant returned to address corrections 10/1/2020 MANUEL GARCIA
Plan Check Approved 11/6/2020 ALFREDO JARA
Issued 11/16/2020 APPLICANT
Building Plans Picked Up 11/18/2020 APPLICANT
CofO in Progress 6/18/2021 RAUL BARAJAS
Permit Finaled 7/10/2021 DEROLD HAUFF
Permit Finaled 7/10/2021 DEROLD HAUFF
CofO Issued 7/10/2021 DEROLD HAUFF

Permit Application Clearance Information

Specific Plan Cleared 6/4/2020 MIGUEL GAMBOA
ZI Cleared 6/4/2020 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 11/6/2020 PARISA ZAHABI

Contact Information

Contractor Fc Construction Services Inc; Lic. No.: 1059408-B 410 E AVENUE K-12 STE 105      LANCASTER, CA 93535
Engineer Daugherty,, Daniel Thomas; Lic. No.: C76588 31129 VIA COLINAS STE 707      WESTLAKE VILLAGE, CA 91362
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882
Geologist Daugherty,, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 12/8/2020 Partial Inspection RAUL BARAJAS
Deck 1/20/2021 Approved RAUL BARAJAS
Grounding or Bonding 1/20/2021 Approved RAUL BARAJAS
Enclosure/Fence 2/11/2021 Partial Inspection RAUL BARAJAS
Final 2/26/2021 Not Ready for Inspection RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 2/26/2021 SGSOV Approved RAUL BARAJAS
Final 3/4/2021 Corrections Issued RAUL BARAJAS
Final 5/19/2021 Not Ready for Inspection RAUL BARAJAS
Final 6/18/2021 OK to Issue CofO RAUL BARAJAS