325 N LAS PALMAS AVE 90004

Certificate Information: 325 N LAS PALMAS AVE 90004

Application / Permit
20047-30000-00558
Plan Check / Job No.
B20WL01811
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) Pool per standard plan 268 at rear of the lot.
Permit Issued
Issued on 12/11/2020
Issuing Office
Current Status
CofO Issued on 7/2/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/23/2020 APPLICANT
Assigned to Plan Check Engineer 4/29/2020 KAVIAN REFAHI
Corrections Issued 4/29/2020 KAVIAN REFAHI
Applicant returned to address corrections 6/2/2020 JAHANSHAH POURHASSAN
Applicant returned to address corrections 9/23/2020 PARISA ZAHABI
Applicant returned to address corrections 10/14/2020 RICHARD GARCIA
Plan Check Approved 11/6/2020 ALFREDO JARA
Issued 12/11/2020 APPLICANT
Building Plans Picked Up 12/21/2020 APPLICANT
CofO in Progress 6/14/2021 JOSEPH MCGARRY
Permit Finaled 7/2/2021 DEROLD HAUFF
CofO Issued 7/2/2021 DEROLD HAUFF
Permit Finaled 7/2/2021 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 5/19/2020 NOAH MCCOY
Abandoned oil well approval Cleared 10/2/2020 MATTHEW CRAIG
Miscellaneous Cleared 11/6/2020 KAVIAN REFAHI

Contact Information

Contractor Charles Latham Construction; Lic. No.: 580175-B 22916 ELKWOOD STREET      WEST HILLS, CA 91304
Engineer Biedenbach,, Christopher James; Lic. No.: C74003 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 1/11/2021 Approved CHRIS CHRISTENSEN
Deputy Shotcrete 1/21/2021 Conditional Approval CHRIS CHRISTENSEN
Deck 2/4/2021 Conditional Approval JOSEPH MCGARRY
Pool Piping 2/4/2021 Approved JOSEPH MCGARRY
Rough-Electrical 2/4/2021 Approved JOSEPH MCGARRY
Rough-Plumbing 2/4/2021 Approved JOSEPH MCGARRY
Enclosure/Fence 3/10/2021 Conditional Approval JOSEPH MCGARRY
Excavation/Setback/Form/Re-Bar 4/15/2021 Approved JOSEPH MCGARRY
Final 4/15/2021 Corrections Issued JOSEPH MCGARRY
SGSOV-Seismic Gas S/O Valve 4/15/2021 SGSOV Approved JOSEPH MCGARRY
Equipment Noise Level 4/27/2021 Approved ROBERT CHAVEZ
Final 6/9/2021 OK to Issue CofO JOSEPH MCGARRY