7902 W ZEUS DR 90046

Certificate Information: 7902 W ZEUS DR 90046

Application / Permit
20047-30000-00506
Plan Check / Job No.
B20WL01652
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
New pool with spa.
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofO Issued on 8/8/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2020 APPLICANT
Assigned to Plan Check Engineer 5/6/2020 MANUEL GARCIA
Corrections Issued 5/13/2020 MANUEL GARCIA
Quality Review Completed 5/19/2020 TARIK SAOUD
Applicant returned to address corrections 8/5/2020 MANUEL GARCIA
Green Plans Picked Up 10/14/2020 APPLICANT
Plan Check Approved 11/12/2020 MANUEL GARCIA
Issued 11/24/2020 APPLICANT
Building Plans Picked Up 11/25/2020 APPLICANT
CofO in Progress 8/8/2023 STUART CHAPMAN
Permit Finaled 8/8/2023 DEROLD HAUFF
CofO Issued 8/8/2023 DEROLD HAUFF
Permit Finaled 8/8/2023 DEROLD HAUFF

Permit Application Clearance Information

ZA Case Cleared 6/3/2020 KENTON TRINH
Eng Process Fee Ord 176,300 Cleared 7/24/2020 RENZ SORIANO
Drainage to Storm Drain Cleared 8/19/2020 SAM NAVID
Grading Pre-Inspection Cleared 11/9/2020 MANUEL GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/31/2020 Partial Inspection RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 2/19/2021 Partial Approval RAUL BARAJAS
Deputy Other (see comments) 2/24/2021 Conditional Approval RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 3/25/2021 Partial Approval BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 4/19/2021 Partial Approval RAUL BARAJAS
Pre-Gunite 5/19/2021 Corrections Issued BRIAN SULLIVAN
Pre-Gunite 5/27/2021 Approved RAUL BARAJAS
Deputy Shotcrete 6/2/2021 No Access for Inspection ELMER BLAND
Deck 9/19/2022 Approved RAUL BARAJAS
Enclosure/Fence 11/17/2022 Corrections Issued RAUL BARAJAS
Rough-Electrical 11/17/2022 Not Ready for Inspection RAUL BARAJAS
Enclosure/Fence 12/1/2022 Approved RAUL BARAJAS
Excavation/Setback/Form/Re-Bar 12/1/2022 Approved RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 12/1/2022 SGSOV Not Ready RAUL BARAJAS
Final 5/3/2023 Corrections Issued STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Approved STUART CHAPMAN
Equipment Noise Level 5/16/2023 No Access for Inspection ZEYDI STEWART
Pool Equipment Noise Test 5/23/2023 Approved ZEYDI STEWART
Final 8/1/2023 OK to Issue CofO STUART CHAPMAN