173 N CARMELINA AVE 90049
Certificate Information: 173 N CARMELINA AVE 90049
- Application / Permit
- 20047-30000-00426
- Plan Check / Job No.
- B20WL01390
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL (17' X 36'-8") & SPA (7' X 8'-6") AT REAR OF THE LOT. PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 12/14/2020
- Issuing Office
- Current Status
- CofO Issued on 2/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 4/2/2020 | ALFREDO JARA |
| Corrections Issued | 4/13/2020 | ALFREDO JARA |
| Quality Review Completed | 4/24/2020 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 12/7/2020 | ALFREDO JARA |
| Issued | 12/14/2020 | APPLICANT |
| Building Plans Picked Up | 12/14/2020 | APPLICANT |
| CofO in Progress | 2/9/2022 | JUAN VALENZUELA |
| Permit Finaled | 2/18/2022 | DANIEL ORRANTE |
| CofO Issued | 2/18/2022 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 12/7/2020 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 12/7/2020 | ALFREDO JARA |
Contact Information
| Contractor | Valle/Reinis Builders Inc; Lic. No.: 839178-B | 11661 SAN VICENTE BLVD STE 302 LOS ANGELES, CA 90049 |
| Engineer | Azizisefat,, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
| Engineer | Dermendjian,, Raffi Hrag; Lic. No.: C88261 | 9325 SHOSHONE AVENUE NORTHRIDGE, CA 91325 |
| Engineer | Walter,, Scott John; Lic. No.: GE2476 | 14428 HAMLIN ST STE 200 VAN NUYS, CA 91401 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/10/2021 | Conditional Approval | JUAN VALENZUELA |
| Deputy Shotcrete | 3/15/2021 | Conditional Approval | JUAN VALENZUELA |
| Rough-Plumbing | 6/7/2021 | Approved | KENNETH NAGLE |
| Grounding or Bonding | 10/14/2021 | Approved | JUAN VALENZUELA |
| Enclosure/Fence | 10/22/2021 | Not Ready for Inspection | JUAN VALENZUELA |
| Enclosure/Fence | 11/9/2021 | Corrections Issued | STEPHANIE SWANSON |
| Enclosure/Fence | 11/12/2021 | Partial Approval | RYAN SALAZAR |
| Equipment Noise Level | 11/23/2021 | Approved | AGUSTIN ALVAREZMORALES |
| Excavation/Setback/Form/Re-Bar | 11/24/2021 | Approved | JUAN VALENZUELA |
| Final | 11/24/2021 | Corrections Issued | JUAN VALENZUELA |
| Pre-Gunite | 11/24/2021 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Approved | JUAN VALENZUELA |
| Enclosure/Fence | 11/29/2021 | Corrections Issued | STEPHANIE SWANSON |
| Pool/Spa Cover | 11/29/2021 | Conditional Approval | STEPHANIE SWANSON |
| Enclosure/Fence | 1/27/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Enclosure/Fence | 2/8/2022 | Approved | JUAN VALENZUELA |
| Final | 2/8/2022 | OK to Issue CofO | JUAN VALENZUELA |