214 N ASHDALE PL 90049
Certificate Information: 214 N ASHDALE PL 90049
- Application / Permit
- 20047-30000-00175
- Plan Check / Job No.
- B20WL00609
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) KOI POND AT (E) SFD. PER LA CITY STANDARD PLANS #268
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/5/2020 | ALFREDO JARA |
| Corrections Issued | 2/5/2020 | ALFREDO JARA |
| Plan Check Approved | 2/20/2020 | PARISA ZAHABI |
| Plan Check Approved | 2/28/2020 | PARISA ZAHABI |
| Issued | 2/28/2020 | LADBS |
| CofO in Progress | 10/29/2020 | CARLOS MATAMOROS |
| CofO Issued | 11/17/2020 | VINCENT COTTON |
| Permit Finaled | 11/17/2020 | VINCENT COTTON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 2/19/2020 | ALFREDO JARA |
Contact Information
| Contractor | Cochrane Jonathan F Construction Inc; Lic. No.: 486666-B | 9111 S LA CIENEGA BLVD #110 INGLEWOOD, CA 90301 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/15/2020 | Corrections Issued | CARLOS MATAMOROS |
| Rough-Electrical | 6/15/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Rough-Plumbing | 6/15/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/17/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 6/19/2020 | Approved | CARLOS MATAMOROS |
| Grounding or Bonding | 6/19/2020 | Approved | CARLOS MATAMOROS |
| Pool Piping | 6/19/2020 | Approved | CARLOS MATAMOROS |
| Rough-Electrical | 6/19/2020 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 9/28/2020 | Corrections Issued | CARLOS MATAMOROS |
| Final | 9/28/2020 | Corrections Issued | CARLOS MATAMOROS |
| Pre-Gunite | 9/28/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/28/2020 | SGSOV Not Ready | CARLOS MATAMOROS |
| ELECTRICAL-Final | 10/5/2020 | Approved | CARLOS MATAMOROS |
| Final | 10/5/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Pre-Gunite | 10/5/2020 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Not Ready | CARLOS MATAMOROS |
| Enclosure/Fence | 10/6/2020 | Approved | CARLOS MATAMOROS |
| Pool Equipment Noise Test | 10/8/2020 | Approved | ROBERT CHAVEZ |
| ELECTRICAL-Final | 10/9/2020 | Approved | CARLOS MATAMOROS |
| Final | 10/9/2020 | Partial Approval | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 10/9/2020 | SGSOV Approved | CARLOS MATAMOROS |