1833 N FRANKLIN CANYON DR 90210

Certificate Information: 1833 N FRANKLIN CANYON DR 90210

Application / Permit
20047-30000-00005
Plan Check / Job No.
B20WL00030
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
(N) pool/spa per standard plans #268
Permit Issued
Issued on 1/3/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/3/2020 APPLICANT
Assigned to Plan Check Engineer 1/3/2020 ALFREDO JARA
Corrections Issued 1/3/2020 ALFREDO JARA
Plan Check Approved 1/3/2020 KAVIAN REFAHI
Issued 1/3/2020 LADBS
CofO in Progress 4/28/2021 ANTHONY MCDOWALL
CofO Issued 6/10/2021 VINCENT COTTON
Permit Finaled 6/10/2021 VINCENT COTTON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/3/2020 HISASHI KOBAYAKAWA
Watercourse Cleared 1/3/2020 MAHELET GEBEYHU
ZA Case Cleared 1/3/2020 SARAH GOLDMAN

Contact Information

Contractor Ample Construction; Lic. No.: 957060-B 3857 BIRCH ST STU 333      NEWPORT BEACH, CA 92660
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Proofing Certificate 2/18/2020 Not Ready for Inspection ANTHONY MCDOWALL
Pre-Gunite 2/18/2020 Corrections Issued ANTHONY MCDOWALL
FLOOD-Proofing Certificate 2/25/2020 Not Ready for Inspection ANTHONY MCDOWALL
Pre-Gunite 2/25/2020 Corrections Issued ANTHONY MCDOWALL
Excavation/Setback/Form/Re-Bar 2/27/2020 Approved ANTHONY MCDOWALL
FLOOD-Elevation Certificate 2/27/2020 Approved ANTHONY MCDOWALL
Pre-Inspection 10/29/2020 No Access for Inspection ANTHONY MCDOWALL
FLOOD-Proofing Certificate 2/19/2021 Approved ANTHONY MCDOWALL
Final 2/19/2021 Corrections Issued ANTHONY MCDOWALL
Pre-Gunite 2/19/2021 Approved ANTHONY MCDOWALL
SGSOV-Seismic Gas S/O Valve 2/19/2021 SGSOV Not Ready ANTHONY MCDOWALL
Pool Equipment Noise Test 3/8/2021 Approved DA LIU
Final 3/17/2021 Not Ready for Inspection ANTHONY MCDOWALL
SGSOV-Seismic Gas S/O Valve 3/17/2021 SGSOV Approved ANTHONY MCDOWALL
Final 4/14/2021 Corrections Issued ANTHONY MCDOWALL
Final 4/28/2021 OK to Issue CofO ANTHONY MCDOWALL