220 E BARBOUR ST 90293
Certificate Information: 220 E BARBOUR ST 90293
- Application / Permit
- 20047-20000-02378
- Plan Check / Job No.
- B20VN16830
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW POOL & SPA - 1 OF 2
- Permit Issued
- Issued on 4/22/2021
- Issuing Office
- Current Status
- CofO Issued on 9/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2021 | JESSE ARELLANO |
| Corrections Issued | 1/31/2021 | JESSE ARELLANO |
| Applicant returned to address corrections | 3/24/2021 | JESSE ARELLANO |
| Issued | 4/22/2021 | APPLICANT |
| Building Plans Picked Up | 4/22/2021 | APPLICANT |
| CofO in Progress | 9/20/2021 | JOHN MATTILLO |
| Permit Finaled | 9/23/2021 | BRUCE TODD |
| CofO Issued | 9/23/2021 | BRUCE TODD |
| Permit Finaled | 9/23/2021 | BRUCE TODD |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Pool Logic La; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD PASADENA, CA 91106 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/29/2021 | Not Ready for Inspection | MARIAN PODPORA |
| Pre-Gunite | 6/1/2021 | Corrections Issued | MARIAN PODPORA |
| Pre-Gunite | 6/3/2021 | Not Ready for Inspection | MARIAN PODPORA |
| Pre-Gunite | 6/8/2021 | Approved | MARIAN PODPORA |
| Deck | 6/16/2021 | No Access for Inspection | MARIAN PODPORA |
| Deck | 6/24/2021 | Corrections Issued | MARIAN PODPORA |
| Deck | 6/29/2021 | Corrections Issued | MARIAN PODPORA |
| Pool Equipment Noise Test | 7/9/2021 | Approved | AGUSTIN ALVAREZMORALES |
| Excavation/Setback/Form/Re-Bar | 7/12/2021 | Conditional Approval | MARIAN PODPORA |
| Final | 7/12/2021 | Corrections Issued | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 7/12/2021 | SGSOV Not Ready | MARIAN PODPORA |
| Excavation/Setback/Form/Re-Bar | 7/22/2021 | Not Ready for Inspection | MARIAN PODPORA |
| Final | 7/22/2021 | Not Ready for Inspection | MARIAN PODPORA |
| Gas Piping or Gas Test | 7/22/2021 | Approved | MARIAN PODPORA |
| SGSOV-Seismic Gas S/O Valve | 7/22/2021 | SGSOV Approved | MARIAN PODPORA |
| Excavation/Setback/Form/Re-Bar | 8/19/2021 | Approved | MARIAN PODPORA |
| Final | 8/19/2021 | Conditional Approval | MARIAN PODPORA |