20532 W BIRMINGHAM WAY 91326
Certificate Information: 20532 W BIRMINGHAM WAY 91326
- Application / Permit
- 20047-20000-02333
- Plan Check / Job No.
- B20VN16554
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17' X 42'-6" POOL W/ 6' X 8' SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 2/19/2021
- Issuing Office
- Current Status
- CofO Issued on 12/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/24/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | RAPHAEL ROSAS |
| Corrections Issued | 1/14/2021 | RAPHAEL ROSAS |
| Issued | 2/19/2021 | APPLICANT |
| Building Plans Picked Up | 2/26/2021 | APPLICANT |
| CofO in Progress | 12/7/2022 | DAVID SCANTLIN |
| Permit Finaled | 12/21/2022 | JOHN JANSON |
| CofO Issued | 12/21/2022 | JOHN JANSON |
| Permit Finaled | 12/21/2022 | JOHN JANSON |
Permit Application Clearance Information
| "T" removal | Cleared | 2/5/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 2/5/2021 | LAUREN PADICK |
| Miscellaneous | Cleared | 2/5/2021 | LAUREN PADICK |
| Tract Map conditions | Cleared | 2/5/2021 | LAUREN PADICK |
| Tract Map conditions | Cleared | 2/5/2021 | LAUREN PADICK |
| Tract Map conditions | Cleared | 2/5/2021 | LAUREN PADICK |
| ZA Case | Cleared | 2/5/2021 | LAUREN PADICK |
| ZA Case | Cleared | 2/5/2021 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 2/19/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Pool Logic La; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD PASADENA, CA 91106 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/20/2021 | Approved | DAVID SCANTLIN |
| Deck | 5/4/2021 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 7/13/2021 | Approved | DAVID SCANTLIN |
| Equipment Noise Level | 8/16/2021 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 8/16/2021 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 8/17/2021 | Approved | DAVID SCANTLIN |
| Final | 8/17/2021 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 8/17/2021 | SGSOV Approved | DAVID SCANTLIN |
| Final | 12/7/2022 | OK to Issue CofO | DAVID SCANTLIN |