13161 W HARTSOOK ST 91423

Certificate Information: 13161 W HARTSOOK ST 91423

Application / Permit
20047-20000-02328
Plan Check / Job No.
B20VN16532
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED NEW IRR SHAPED (32'X13') NEW POOL W/ SPA (7'X7') PER CITY STD PLAN #268- SEE COMMENTS
Permit Issued
Issued on 4/27/2021
Issuing Office
Current Status
CofO Issued on 8/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2020 APPLICANT
Assigned to Plan Check Engineer 1/8/2021 HAYATO TSUCHIYA
Corrections Issued 1/10/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 4/16/2021 RARES BODEA
Plan Check Approved 4/16/2021 RARES BODEA
No Progress 4/16/2021 RARES BODEA
Plan Check Approved 4/27/2021 RARES BODEA
Issued 4/27/2021 APPLICANT
Building Plans Picked Up 4/30/2021 APPLICANT
CofO in Progress 8/16/2021 CHRISTOPHE COCHRAN
Permit Finaled 8/23/2021 MICHAEL SMITH
CofO Issued 8/23/2021 MICHAEL SMITH
Permit Finaled 8/23/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 3/31/2021 RIDWAN HARDY

Contact Information

Contractor Custom Derian Pools & Construction; Lic. No.: 977981-C53 21271 BURBANK BLVD #110      WOODLAND HILLS, CA 91367
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 5/10/2021 Not Ready for Inspection ARAM AVEDISIAN
Pre-Gunite 5/11/2021 Approved RICHARD DOCKUS
Deputy Shotcrete 5/17/2021 Conditional Approval DANIEL ORRANTE
Gas Piping or Gas Test 5/25/2021 Approved RICHARD DOCKUS
Rough-Electrical 5/25/2021 Approved RICHARD DOCKUS
Deck 6/7/2021 Not Ready for Inspection RICHARD DOCKUS
Enclosure/Fence 7/20/2021 Corrections Issued CHRISTOPHE COCHRAN
Enclosure/Fence 8/4/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 8/16/2021 Approved CHRISTOPHE COCHRAN
Equipment Noise Level 8/16/2021 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 8/16/2021 Approved CHRISTOPHE COCHRAN
Final 8/16/2021 OK to Issue CofO CHRISTOPHE COCHRAN
PLUMBING-Final 8/16/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 8/16/2021 SGSOV Approved CHRISTOPHE COCHRAN