12261 W KLING ST 91607
Certificate Information: 12261 W KLING ST 91607
- Application / Permit
- 20047-20000-02324
- Plan Check / Job No.
- B20VN16521
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 32' X 17' SWIMMING POOL WITH ATTACHED 7' X 6' SPA PER LA CITY STANDARD PLAN #268
- Permit Issued
- Issued on 3/2/2021
- Issuing Office
- Current Status
- CofO Issued on 10/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2020 | GURUNATH NESARAJAH |
| Corrections Issued | 1/3/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 2/22/2021 | GURUNATH NESARAJAH |
| Issued | 3/2/2021 | APPLICANT |
| CofO in Progress | 10/5/2021 | ARAM AVEDISIAN |
| CofO Issued | 10/5/2021 | MICHAEL SMITH |
| Permit Finaled | 10/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/8/2021 | PABLO ESTRADA |
Contact Information
| Contractor | Premier Pool Plastering; Lic. No.: 625132-C53 | 14520 FOOTHILL BLVD SYLMAR, CA 91342 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/25/2021 | Approved | ARAM AVEDISIAN |
| Gas Piping or Gas Test | 3/25/2021 | Approved | ARAM AVEDISIAN |
| Grounding or Bonding | 3/25/2021 | Partial Approval | ARAM AVEDISIAN |
| Pool Piping | 3/25/2021 | Approved | ARAM AVEDISIAN |
| Pre-Gunite | 3/25/2021 | Approved | ARAM AVEDISIAN |
| Rough-Electrical | 3/25/2021 | Approved | ARAM AVEDISIAN |
| Deck | 4/19/2021 | Approved | ARAM AVEDISIAN |
| Enclosure/Fence | 5/25/2021 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 6/1/2021 | Partial Inspection | MICHEL ABAJAN |
| Enclosure/Fence | 6/1/2021 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 6/1/2021 | Partial Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 6/1/2021 | SGSOV Not Ready | MICHEL ABAJAN |
| Final | 6/15/2021 | Corrections Issued | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 6/15/2021 | SGSOV Approved | ARAM AVEDISIAN |
| Pool Equipment Noise Test | 6/16/2021 | Approved | FELIPE PENICHE |
| Final | 10/5/2021 | OK to Issue CofO | ARAM AVEDISIAN |