3851 S SYCAMORE AVE 90008
Certificate Information: 3851 S SYCAMORE AVE 90008
- Application / Permit
- 20047-20000-02290
- Plan Check / Job No.
- B20VN16293
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20' X 33' W/ 6' X 8' SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 3/26/2021
- Issuing Office
- Current Status
- Issued on 3/26/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2020 | RAPHAEL ROSAS |
| Corrections Issued | 12/29/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 3/4/2021 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| Issued | 3/26/2021 | APPLICANT |
Permit Application Clearance Information
| Construction near power lines | Cleared | 2/9/2021 | RIDWAN HARDY |
| Construction within easement | Cleared | 2/9/2021 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 3/4/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | J A B S Pools And Spas; Lic. No.: 936142-C53 | 8055 MATILIJA AVENUE PANORAMA CITY, CA 91402 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/16/2021 | Corrections Issued | FREDDIE RIVERA |
| Rough-Electrical | 4/16/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Rough-Plumbing | 4/16/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Pre-Gunite | 4/21/2021 | Approved | FREDDIE RIVERA |
| Rough-Electrical | 4/21/2021 | Off-Hour Fees Due | |
| Rough-Electrical | 4/21/2021 | Partial Approval | FREDDIE RIVERA |
| Rough-Plumbing | 4/21/2021 | Approved | FREDDIE RIVERA |
| Rough-Plumbing | 4/21/2021 | Off-Hour Fees Due | |
| Deputy Shotcrete | 4/28/2021 | No Access for Inspection | DAVID FEILER |
| Deck | 5/21/2021 | Partial Inspection | DAVID FEILER |
| Grounding or Bonding | 5/21/2021 | Corrections Issued | DAVID FEILER |
| Deck | 5/28/2021 | Approved | DAVID FEILER |
| Grounding or Bonding | 5/28/2021 | Approved | DAVID FEILER |
| Enclosure/Fence | 6/14/2021 | Corrections Issued | DAVID FEILER |
| Enclosure/Fence | 6/15/2021 | Approved | DAVID FEILER |
| Pool Equipment Noise Test | 6/30/2021 | Approved | AGUSTIN ALVAREZMORALES |
| Excavation/Setback/Form/Re-Bar | 7/2/2021 | Approved | FREDDIE RIVERA |
| Final | 7/2/2021 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Approved | FREDDIE RIVERA |
| Final | 7/8/2021 | Not Ready for Inspection | FREDDIE RIVERA |