11963 N MIRABEL WAY 91326
Certificate Information: 11963 N MIRABEL WAY 91326
- Application / Permit
- 20047-20000-02285
- Plan Check / Job No.
- B20VN16270
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 13'-4" X 24'-4" POOL W/ 5' X 6' SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 1/25/2021
- Issuing Office
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2020 | RAPHAEL ROSAS |
| Corrections Issued | 12/25/2020 | RAPHAEL ROSAS |
| Plan Check Approved | 1/25/2021 | RAPHAEL ROSAS |
| Issued | 1/25/2021 | APPLICANT |
| CofO in Progress | 9/2/2021 | DAVID SCANTLIN |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| "T" removal | Cleared | 1/5/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/5/2021 | DANG NGUYEN |
| Miscellaneous | Cleared | 1/5/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 1/5/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 1/5/2021 | DANG NGUYEN |
| Tract Map conditions | Cleared | 1/5/2021 | DANG NGUYEN |
| ZA Case | Cleared | 1/5/2021 | DANG NGUYEN |
| ZA Case | Cleared | 1/5/2021 | DANG NGUYEN |
| Grading Pre-Inspection | Cleared | 1/25/2021 | RAPHAEL ROSAS |
Contact Information
| Contractor | Swink'S Creations Inc; Lic. No.: 487997-C53 | 3105 HOOP PINE PLACE SIMI VALLEY, CA 93065 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/2/2021 | Approved | DAVID SCANTLIN |
| Rough-Electrical | 3/2/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Rough-Plumbing | 3/2/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Deputy Shotcrete | 3/3/2021 | Partial Approval | DAVID SCANTLIN |
| Deputy Shotcrete | 3/5/2021 | Partial Approval | DAVID SCANTLIN |
| Deputy Shotcrete | 3/16/2021 | Partial Approval | DAVID SCANTLIN |
| Rough-Electrical | 3/31/2021 | Approved | DAVID SCANTLIN |
| Rough-Plumbing | 3/31/2021 | Approved | DAVID SCANTLIN |
| Deck | 4/15/2021 | Approved | SEAN WIRCH |
| Deck | 4/15/2021 | Off-Hour Fees Due | |
| Enclosure/Fence | 6/14/2021 | Corrections Issued | DAVID SCANTLIN |
| Enclosure/Fence | 6/17/2021 | Approved | JOSEPH SAGEN |
| Equipment Noise Level | 7/15/2021 | Approved | ALFREDO FLORES |
| ELECTRICAL-Final | 7/16/2021 | Approved | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 7/16/2021 | Approved | DAVID SCANTLIN |
| Final | 7/16/2021 | Corrections Issued | DAVID SCANTLIN |
| PLUMBING-Final | 7/16/2021 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 9/1/2021 | Approved | DAVID SCANTLIN |
| Final | 9/1/2021 | OK to Issue CofO | DAVID SCANTLIN |
| PLUMBING-Final | 9/1/2021 | Approved | DAVID SCANTLIN |