12221 W VALLEYHEART DR 91604

Certificate Information: 12221 W VALLEYHEART DR 91604

Application / Permit
20047-20000-02161
Plan Check / Job No.
B20VN15652
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16' X 30' POOL W/ 6' X 6' SPA WITHIN POOL SHELL PER LA CITY STANDARD PLAN #268. SEE COMMENTS.
Permit Issued
Issued on 2/9/2021
Issuing Office
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/6/2020 APPLICANT
Assigned to Plan Check Engineer 12/14/2020 ROSENDO MEDINA
Corrections Issued 12/15/2020 ROSENDO MEDINA
Plan Check Approved 1/19/2021 JENNIFER LEE
Issued 2/9/2021 APPLICANT
CofO in Progress 7/23/2021 ARAM AVEDISIAN
Permit Finaled 8/7/2021 MICHAEL SMITH
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Jr Pool & Spa Services; Lic. No.: 771197-C53 P O BOX 5249      NORTH HOLLYWOOD, CA 91616
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 3/1/2021 Approved ARAM AVEDISIAN
Pre-Gunite 3/1/2021 Conditional Approval ARAM AVEDISIAN
Deputy Shotcrete 3/2/2021 Conditional Approval ARAM AVEDISIAN
Deck 3/31/2021 Approved ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 6/24/2021 Approved ARAM AVEDISIAN
Final 6/24/2021 Not Ready for Inspection ARAM AVEDISIAN
Pre-Gunite 6/24/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/24/2021 SGSOV Approved ARAM AVEDISIAN
Final 7/21/2021 Corrections Issued ARAM AVEDISIAN
Equipment Noise Level 7/23/2021 Approved FELIPE PENICHE
Final 7/23/2021 OK to Issue CofO ARAM AVEDISIAN
Pool Equipment Noise Test 7/23/2021 Approved FELIPE PENICHE