7806 N COWPER AVE 91304

Certificate Information: 7806 N COWPER AVE 91304

Application / Permit
20047-20000-02113
Plan Check / Job No.
B20VN15369
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14'-6" X 29'-0" SWIMMING POOL AND 8' X 8' SPA WITHIN PER STANDARD PLAN #270
Permit Issued
Issued on 1/10/2021
Issuing Office
Current Status
CofO Issued on 5/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/25/2020 APPLICANT
Assigned to Plan Check Engineer 12/4/2020 JEROME MAGAT PALMA
Corrections Issued 12/21/2020 JEROME MAGAT PALMA
Plan Check Approved 1/9/2021 JEROME MAGAT PALMA
Issued 1/10/2021 APPLICANT
CofO in Progress 5/14/2021 DAVID STEPANYAN
CofO Issued 5/14/2021 MICHAEL SMITH
Permit Finaled 5/14/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/7/2020 JEROME MAGAT PALMA

Contact Information

Contractor Vitoli Builders Inc; Lic. No.: 1043914-B 23480 PARK SORRENTO #201-A      CALABASAS, CA 91302
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 2/3/2021 Corrections Issued DAVID STEPANYAN
Pre-Gunite 2/5/2021 Not Ready for Inspection DAVID STEPANYAN
Deputy Shotcrete 2/10/2021 Conditional Approval DAVID STEPANYAN
Pre-Gunite 2/10/2021 Approved DAVID STEPANYAN
Final 4/26/2021 Corrections Issued DAVID STEPANYAN
Grounding or Bonding 4/26/2021 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Approved DAVID STEPANYAN
Enclosure/Fence 5/10/2021 Not Ready for Inspection DAVID STEPANYAN
Equipment Noise Level 5/10/2021 Approved ALFREDO FLORES
Grounding or Bonding 5/10/2021 Approved DAVID STEPANYAN
Deputy Shotcrete 5/11/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 5/11/2021 Approved DAVID STEPANYAN
Enclosure/Fence 5/11/2021 Approved DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 5/11/2021 Approved DAVID STEPANYAN
Final 5/11/2021 OK to Issue CofO DAVID STEPANYAN
Pool/Spa Cover 5/11/2021 Approved DAVID STEPANYAN