4931 N MATILIJA AVE 91423

Certificate Information: 4931 N MATILIJA AVE 91423

Application / Permit
20047-20000-02100
Plan Check / Job No.
B20VN15304
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 36' X 16' SWIMMING POOL WITH ATTACHED 7' X 7' SPA PER LA CITY STANDARD PLAN #265
Permit Issued
Issued on 2/27/2021
Issuing Office
Current Status
CofO Issued on 8/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/24/2020 APPLICANT
Assigned to Plan Check Engineer 12/3/2020 GURUNATH NESARAJAH
Corrections Issued 12/6/2020 GURUNATH NESARAJAH
Plan Check Approved 2/25/2021 GURUNATH NESARAJAH
Issued 2/27/2021 APPLICANT
Building Plans Picked Up 3/9/2021 APPLICANT
CofO in Progress 11/9/2021 MISAEL ESPARZA
Permit Finaled 8/3/2022 DANIEL ORRANTE
CofO Issued 8/3/2022 DANIEL ORRANTE
Permit Finaled 8/3/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 2/25/2021 JOHN BACON

Contact Information

Contractor J H K Contractors Inc; Lic. No.: 835178-B 3216-A SANTA MONICA BLVD      SANTA MONICA, CA 90404
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/6/2021 Corrections Issued CHARLES POWELL
Excavation/Setback/Form/Re-Bar 4/13/2021 Approved CHARLES POWELL
Pre-Gunite 4/13/2021 Approved CHARLES POWELL
Deputy Shotcrete 5/14/2021 Conditional Approval DANIEL ORRANTE
Gas Piping or Gas Test 5/28/2021 Approved CHARLES POWELL
Enclosure/Fence 8/25/2021 Approved CHARLES POWELL
Final 9/23/2021 Partial Inspection MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 9/23/2021 SGSOV Not Ready MISAEL ESPARZA
Final 10/1/2021 Corrections Issued MISAEL ESPARZA
SGSOV-Seismic Gas S/O Valve 10/1/2021 SGSOV Approved MISAEL ESPARZA
Pool Equipment Noise Test 10/15/2021 Approved ALFREDO FLORES
Final 10/26/2021 Not Ready for Inspection MISAEL ESPARZA
Final 11/5/2021 OK to Issue CofO MISAEL ESPARZA