17025 W EMPANADA PL 91436
Certificate Information: 17025 W EMPANADA PL 91436
- Application / Permit
- 20047-20000-02099
- Plan Check / Job No.
- B20VN15296
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 13' X 31' SWIMMING POOL AND 7' X 7' SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAIL.
- Permit Issued
- Issued on 12/31/2020
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 12/4/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 12/6/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/17/2020 | JEROME MAGAT PALMA |
| Issued | 12/31/2020 | APPLICANT |
| CofO in Progress | 4/25/2022 | DAVID SANDOVAL |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 12/6/2020 | JEROME MAGAT PALMA |
| ZA Case | Cleared | 12/9/2020 | LAUREN PADICK |
Contact Information
| Contractor | Custom Derian Pools; Lic. No.: 977981-C53 | P O BOX 1352 MOORPARK, CA 93020 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 4/8/2021 | Approved | RONALD COWAN |
| Rough-Electrical | 4/28/2021 | Approved | RONALD COWAN |
| Deck | 5/17/2021 | Approved | RONALD COWAN |
| Gas Piping or Gas Test | 5/17/2021 | Approved | RONALD COWAN |
| Deck | 6/9/2021 | Approved | RONALD COWAN |
| Enclosure/Fence | 11/19/2021 | Corrections Issued | PETER FOLLING |
| Enclosure/Fence | 12/6/2021 | No Access for Inspection | ROBERT GOLD |
| Enclosure/Fence | 12/13/2021 | Partial Inspection | ROBERT GOLD |
| Enclosure/Fence | 12/20/2021 | Approved | DAVID SANDOVAL |
| Equipment Noise Level | 1/11/2022 | Approved | FELIPE PENICHE |
| Pool Equipment Noise Test | 1/11/2022 | Approved | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 1/12/2022 | Approved | DAVID SANDOVAL |
| Final | 1/12/2022 | Partial Approval | DAVID SANDOVAL |
| SGSOV-Seismic Gas S/O Valve | 1/12/2022 | SGSOV Approved | DAVID SANDOVAL |
| Final | 4/25/2022 | OK to Issue CofO | DAVID SANDOVAL |