2246 N HARWOOD ST 90031
Certificate Information: 2246 N HARWOOD ST 90031
- Application / Permit
- 20047-20000-02093
- Plan Check / Job No.
- B20VN15213
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 27' POOL AND 6' X 7' SPA WITHIN PER STANDARD PLAN #268 AND ENGINEER DETAIL.
- Permit Issued
- Issued on 1/15/2021
- Issuing Office
- Current Status
- CofO Corrected on 5/21/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/22/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2020 | ROSENDO MEDINA |
| Corrections Issued | 12/2/2020 | ROSENDO MEDINA |
| Plan Check Approved | 1/14/2021 | JEROME MAGAT PALMA |
| Issued | 1/15/2021 | APPLICANT |
| CofO in Progress | 5/17/2021 | KATHRYN BUTTERWORTH |
| CofO Issued-Status Void | 5/19/2021 | DEROLD HAUFF |
| Permit Finaled-Status Void | 5/19/2021 | DEROLD HAUFF |
| Re-Activate Permit | 5/21/2021 | DEROLD HAUFF |
| Permit Finaled | 5/21/2021 | DEROLD HAUFF |
| CofO Corrected | 5/21/2021 | DEROLD HAUFF |
| Permit Finaled | 5/21/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 12/24/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Moderno Pools Inc; Lic. No.: 862353-C53 | 23890 COOPER HILL DR SUITE #225 VALENCIA, CA 91354 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pool Piping | 2/18/2021 | Approved | HAMIK HARTOUNIAN |
| Rough-Electrical | 2/18/2021 | Approved | HAMIK HARTOUNIAN |
| Grounding or Bonding | 3/1/2021 | Partial Approval | COREY HUPP |
| Deck | 3/8/2021 | Approved | CRAIG VAUGHAN |
| Enclosure/Fence | 4/16/2021 | Corrections Issued | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 5/6/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Final | 5/6/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Pre-Gunite | 5/6/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 5/6/2021 | SGSOV Not Required | KATHRYN BUTTERWORTH |
| Pool Equipment Noise Test | 5/12/2021 | Approved | ROBERT CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 5/17/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 5/17/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Pre-Gunite | 5/17/2021 | Approved | KATHRYN BUTTERWORTH |