8804 W LOOKOUT MOUNTAIN AVE 90046
Certificate Information: 8804 W LOOKOUT MOUNTAIN AVE 90046
- Application / Permit
- 20047-20000-02089
- Plan Check / Job No.
- B20VN15199
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 10' DIAMETER SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 12/1/2020
- Issuing Office
- Current Status
- CofO Issued on 4/15/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/25/2020 | RAPHAEL ROSAS |
| Issued | 12/1/2020 | APPLICANT |
| CofO in Progress | 10/27/2021 | RAUL BARAJAS |
| Permit Finaled | 4/15/2023 | DANIEL ORRANTE |
| CofO Issued | 4/15/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/15/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/29/2020 | RAPHAEL ROSAS |
Contact Information
| Contractor | Noga Pool And Spa Inc; Lic. No.: 946647-C53 | 5739 KANAN ROAD #639 AGOURA HILLS, CA 91301 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 1/29/2021 | Corrections Issued | RAUL BARAJAS |
| Gunite | 2/1/2021 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 4/14/2021 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 5/28/2021 | No Access for Inspection | RAUL BARAJAS |
| Final | 5/28/2021 | Corrections Issued | RAUL BARAJAS |
| Pre-Gunite | 5/28/2021 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/28/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Equipment Noise Level | 6/1/2021 | Approved | ROBERT CHAVEZ |
| Excavation/Setback/Form/Re-Bar | 6/15/2021 | Approved | RAUL BARAJAS |
| Final | 6/15/2021 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 6/15/2021 | SGSOV Approved | RAUL BARAJAS |
| Final | 7/12/2021 | Not Ready for Inspection | RICHARD STEINBACH |
| Final | 9/1/2021 | Corrections Issued | BRAD BESCOS |
| Final | 10/12/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 10/20/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Final | 10/27/2021 | OK to Issue CofO | RAUL BARAJAS |