5231 N MONTE BONITO DR 90041
Certificate Information: 5231 N MONTE BONITO DR 90041
- Application / Permit
- 20047-20000-02051
- Plan Check / Job No.
- B20VN14914
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 32'X16' SWIMMING POOL W/ SPA PER CITY STD PLAN #265 W/ ADDENDUM DETAIL & POOL COVER TROUGH DETAIL.
- Permit Issued
- Issued on 3/4/2021
- Issuing Office
- Current Status
- CofO Issued on 1/6/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 11/29/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/18/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 2/18/2021 | HAYATO TSUCHIYA |
| Issued | 3/4/2021 | APPLICANT |
| CofO in Progress | 12/16/2021 | CRAIG VAUGHAN |
| CofO in Progress | 12/17/2021 | CRAIG VAUGHAN |
| Permit Finaled | 1/6/2022 | DEROLD HAUFF |
| CofO Issued | 1/6/2022 | DEROLD HAUFF |
| Permit Finaled | 1/6/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Ahern Construction Corporation; Lic. No.: 687780-B | 3835-R THOUSAND OAKS BLVD #118 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 3/11/2021 | Approved | BRIAN SULLIVAN |
| Enclosure/Fence | 8/10/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Enclosure/Fence | 8/16/2021 | Approved | SCOTT FINNILA |
| Grounding or Bonding | 8/16/2021 | Partial Approval | SCOTT FINNILA |
| Grounding or Bonding | 9/9/2021 | Partial Approval | CHARLES BOGHOSKHAN |
| Excavation/Setback/Form/Re-Bar | 11/18/2021 | Approved | CRAIG VAUGHAN |
| Final | 11/18/2021 | Corrections Issued | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/18/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| Final | 12/7/2021 | Not Ready for Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/7/2021 | SGSOV Not Ready | CRAIG VAUGHAN |
| ELECTRICAL-Final | 12/15/2021 | Approved | CRAIG VAUGHAN |
| Final | 12/15/2021 | OK to Issue CofO | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 12/15/2021 | SGSOV Approved | CRAIG VAUGHAN |