3334 S CLUB DR 90064

Certificate Information: 3334 S CLUB DR 90064

Application / Permit
20047-20000-02039
Plan Check / Job No.
B20VN14787
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 18' X 36' SWIMMING POOL AND 8' X 8' SPA WITHIN PER STANDARD PLAN #268
Permit Issued
Issued on 1/20/2021
Issuing Office
Current Status
CofO Issued on 3/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/13/2020 APPLICANT
Assigned to Plan Check Engineer 11/20/2020 JEROME MAGAT PALMA
Corrections Issued 11/22/2020 JEROME MAGAT PALMA
Plan Check Approved 1/20/2021 JEROME MAGAT PALMA
Issued 1/20/2021 APPLICANT
CofO in Progress 10/25/2021 KEVIN SARGSYAN
Permit Finaled 3/19/2022 DANIEL ORRANTE
CofO Issued 3/19/2022 DANIEL ORRANTE
Permit Finaled 3/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/21/2020 JEROME MAGAT PALMA
Specific Plan Cleared 1/7/2021 LAUREN PADICK

Contact Information

Contractor Bookie Development Inc; Lic. No.: 977585-B 10509 CLARKSON ROAD      LOS ANGELES, CA 90064
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/17/2021 Approved RICHARD ROBLES
Gunite 3/2/2021 Conditional Approval KEVIN SARGSYAN
Pool Piping 3/2/2021 Approved KEVIN SARGSYAN
Rough-Electrical 3/2/2021 Approved KEVIN SARGSYAN
Rough-Plumbing 3/2/2021 Approved KEVIN SARGSYAN
Gas Piping or Gas Test 3/22/2021 Approved KEVIN SARGSYAN
Grounding or Bonding 4/13/2021 Approved KEVIN SARGSYAN
Enclosure/Fence 9/9/2021 No Access for Inspection KEVIN SARGSYAN
Pre-Inspection 9/9/2021 No Access for Inspection KEVIN SARGSYAN
Enclosure/Fence 9/16/2021 Approved KEVIN SARGSYAN
Gunite 9/16/2021 Approved KEVIN SARGSYAN
Pool/Spa Cover 9/16/2021 Approved KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 9/28/2021 Approved KEVIN SARGSYAN
Final 9/28/2021 Corrections Issued KEVIN SARGSYAN
Pool Equipment Noise Test 9/28/2021 Approved ROBERT CHAVEZ
Pre-Gunite 9/28/2021 Approved KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Approved KEVIN SARGSYAN
Final 10/19/2021 Corrections Issued KEVIN SARGSYAN
Final 10/25/2021 OK to Issue CofO KEVIN SARGSYAN