4450 N KATHERINE AVE 91423

Certificate Information: 4450 N KATHERINE AVE 91423

Application / Permit
20047-20000-02004
Plan Check / Job No.
B20VN14577
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 28' X 15' POOL WITH 8' X 8' SPA PER LA CITY STANDARD PLAN 268
Permit Issued
Issued on 11/19/2020
Issuing Office
Current Status
CofO Issued on 8/23/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2020 APPLICANT
Assigned to Plan Check Engineer 11/13/2020 OMAR GARNICA
Plan Check Approved 11/16/2020 OMAR GARNICA
Issued 11/19/2020 APPLICANT
CofO in Progress 7/17/2023 THOMAS FINNILA
Permit Finaled 8/23/2023 RUBEN SALAS
CofO Issued 8/23/2023 RUBEN SALAS
Permit Finaled 8/23/2023 RUBEN SALAS

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Intex Design And Construction Inc; Lic. No.: 981718-C53 15021 VENTURA BLVD STE 520      SHERMAN OAKS, CA 91403
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

MISAEL ESPARZA, (818) 374-1169 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 2/9/2021 Approved CHARLES POWELL
Pre-Gunite 2/9/2021 Approved CHARLES POWELL
Rough-Electrical 2/9/2021 Approved CHARLES POWELL
Rough-Plumbing 2/9/2021 Approved CHARLES POWELL
Deck 3/1/2021 Approved BRENDAN LOONEY
Grounding or Bonding 3/1/2021 Approved BRENDAN LOONEY
Enclosure/Fence 3/17/2021 Approved ARAM AVEDISIAN
Deck 3/26/2021 Not Ready for Inspection ARAM AVEDISIAN
Grounding or Bonding 3/26/2021 Not Ready for Inspection ARAM AVEDISIAN
Pool Equipment Noise Test 3/30/2021 Approved ALFREDO FLORES
ELECTRICAL-Final 3/31/2021 Not Ready for Inspection JOHN HAYES
Excavation/Setback/Form/Re-Bar 3/31/2021 Not Ready for Inspection JOHN HAYES
Final 3/31/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 3/31/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 3/31/2021 SGSOV Not Ready JOHN HAYES
ELECTRICAL-Final 4/8/2021 Approved CHARLES POWELL
Excavation/Setback/Form/Re-Bar 4/8/2021 Approved CHARLES POWELL
Final 4/8/2021 Corrections Issued CHARLES POWELL
PLUMBING-Final 4/8/2021 Approved CHARLES POWELL
SGSOV-Seismic Gas S/O Valve 4/8/2021 SGSOV Approved CHARLES POWELL
Final 10/12/2021 Not Ready for Inspection MISAEL ESPARZA
Final 6/29/2023 Corrections Issued JOHN COLEMAN
Final 7/14/2023 OK to Issue CofO THOMAS FINNILA