1920 N LAUGHLIN PARK DR 90027
Certificate Information: 1920 N LAUGHLIN PARK DR 90027
- Application / Permit
- 20047-20000-01962
- Plan Check / Job No.
- B20VN14339
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 42' X 22' SWIMMING POOL WITH A 10' X 12' ATTACHED SPA PER STD. PLAN #268 - SEE COMMENTS
- Permit Issued
- Issued on 1/6/2021
- Issuing Office
- Current Status
- CofO Issued on 8/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/10/2020 | RARES BODEA |
| Corrections Issued | 11/11/2020 | RARES BODEA |
| Applicant returned to address corrections | 12/2/2020 | OMAR GARNICA |
| Plan Check Approved | 1/6/2021 | OMAR GARNICA |
| Issued | 1/6/2021 | APPLICANT |
| CofO in Progress | 7/25/2022 | ADAM ESCOTO |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
| CofO Issued | 8/20/2022 | DEROLD HAUFF |
| Permit Finaled | 8/20/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/8/2020 | LAUREN PADICK |
| Miscellaneous | Cleared | 12/8/2020 | LAUREN PADICK |
| Private street | Cleared | 12/8/2020 | LAUREN PADICK |
| Specific Plan | Cleared | 12/18/2020 | DANALYNN DOMINGUEZ |
| ZI | Cleared | 12/18/2020 | DANALYNN DOMINGUEZ |
| Grading Pre-Inspection | Cleared | 1/6/2021 | RARES BODEA |
Contact Information
| Contractor | California Pools; Lic. No.: 185102-C53 | 901 CALLE AMANECER #115 SAN CLEMENTE, CA 92673 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 3/8/2021 | Approved | BRIAN SULLIVAN |
| Pre-Gunite | 3/8/2021 | Approved | BRIAN SULLIVAN |
| Deputy Shotcrete | 3/18/2021 | Conditional Approval | ROBERT CORNELL |
| Grounding or Bonding | 6/10/2021 | Partial Approval | BRIAN SULLIVAN |
| Enclosure/Fence | 7/15/2021 | Approved | RAUL BARAJAS |
| Final | 7/15/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pool Equipment Noise Test | 7/15/2022 | Approved | ROBERT CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Final | 7/25/2022 | OK to Issue CofO | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 7/25/2022 | SGSOV Approved | ADAM ESCOTO |