10729 W ESTHER AVE 90064

Certificate Information: 10729 W ESTHER AVE 90064

Application / Permit
20047-20000-01936
Plan Check / Job No.
B20VN14146
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 9' X 32' SWIMMING POOL WITH ATTACHED 5' X 7' SPA PER LA CITY STANDARD PLAN #270
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofO Issued on 7/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 GURUNATH NESARAJAH
Corrections Issued 11/8/2020 GURUNATH NESARAJAH
Plan Check Approved 1/26/2021 GURUNATH NESARAJAH
Issued 2/10/2021 APPLICANT
CofO in Progress 7/7/2021 KENNETH NAGLE
Permit Finaled 7/7/2021 KENNETH NAGLE
CofO Issued 7/7/2021 KENNETH NAGLE
Permit Finaled 7/7/2021 KENNETH NAGLE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/8/2020 GURUNATH NESARAJAH
Specific Plan Cleared 11/19/2020 LAUREN PADICK
Construction near power lines Cleared 12/31/2020 RIDWAN HARDY

Contact Information

Contractor M D M Builders Group; Lic. No.: 933238-B 541 SOUTH SPRING ST STE 213      LOS ANGELES, CA 90013
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/12/2021 Approved RICHARD ROBLES
FLOOD-Elevation Certificate 2/12/2021 Approved RICHARD ROBLES
FLOOD-Proofing Certificate 2/12/2021 Approved RICHARD ROBLES
Pool Piping 2/12/2021 Not Ready for Inspection RICHARD ROBLES
Pre-Gunite 2/12/2021 Approved RICHARD ROBLES
Rough-Electrical 2/12/2021 Not Ready for Inspection RICHARD ROBLES
Rough-Plumbing 2/12/2021 Not Ready for Inspection RICHARD ROBLES
Pool Piping 2/17/2021 Approved RICHARD ROBLES
Rough-Electrical 2/17/2021 Approved RICHARD ROBLES
Rough-Plumbing 2/17/2021 Approved RICHARD ROBLES
Grounding or Bonding 2/22/2021 Partial Approval EVAN COOPER
Final 3/4/2021 Not Ready for Inspection RICHARD ROBLES
SGSOV-Seismic Gas S/O Valve 3/4/2021 SGSOV Approved RICHARD ROBLES
Final 3/10/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Final 3/15/2021 Corrections Issued EVAN COOPER
Final 3/17/2021 Conditional Approval KEVIN SARGSYAN
Pool Equipment Noise Test 4/15/2021 Approved ROBERT CHAVEZ