800 N BROOKTREE ROAD 90272

Certificate Information: 800 N BROOKTREE ROAD 90272

Application / Permit
20047-20000-01935
Plan Check / Job No.
B20VN14130
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED NEW 62'X17' SWIMMING POOL PER CITY STD. PLAN #270
Permit Issued
Issued on 5/20/2021
Issuing Office
Current Status
CofO Issued on 9/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/6/2020 HAYATO TSUCHIYA
Corrections Issued 11/9/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 12/22/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 1/8/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 1/13/2021 HAYATO TSUCHIYA
Applicant returned to address corrections 2/10/2021 JESSE JIMENEZ
Plan Check Approved 5/17/2021 TSE MING HUANG
Issued 5/20/2021 APPLICANT
Building Plans Picked Up 5/25/2021 APPLICANT
CofO in Progress 9/16/2022 KEVIN SARGSYAN
Permit Finaled 9/29/2022 DANIEL ORRANTE
CofO Issued 9/29/2022 DANIEL ORRANTE
Permit Finaled 9/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/13/2021 HAYATO TSUCHIYA
Eng Process Fee Ord 176,300 Cleared 3/2/2021 DINAH GARIN
Miscellaneous Cleared 4/19/2021 JENSON LEE
Watercourse Cleared 5/3/2021 MAHELET GEBEYHU

Contact Information

Contractor Pepe'S Pools Inc; Lic. No.: 1028041-C53 4817 YORK BLVD      LOS ANGELES, CA 90042
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/27/2021 Partial Inspection JOHN KIDWELL
FLOOD-Elevation Certificate 7/30/2021 Approved JUAN VALENZUELA
Pool Piping 7/30/2021 Partial Inspection JUAN VALENZUELA
Pre-Gunite 7/30/2021 Conditional Approval JUAN VALENZUELA
Enclosure/Fence 6/16/2022 Approved JOHN KIDWELL
Grounding or Bonding 6/21/2022 Corrections Issued JOHN KIDWELL
Excavation/Setback/Form/Re-Bar 8/5/2022 Approved KEVIN SARGSYAN
FLOOD-Proofing Certificate 8/5/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 8/5/2022 Corrections Issued KEVIN SARGSYAN
Pre-Gunite 8/5/2022 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 8/5/2022 SGSOV Approved KEVIN SARGSYAN
FLOOD-Proofing Certificate 9/9/2022 Approved KEVIN SARGSYAN
Final 9/9/2022 Not Ready for Inspection KEVIN SARGSYAN
Pre-Gunite 9/9/2022 Not Ready for Inspection KEVIN SARGSYAN
Final 9/15/2022 OK to Issue CofO KEVIN SARGSYAN
Pre-Gunite 9/15/2022 Approved KEVIN SARGSYAN