20330 W WINDSOR LANE 91326
Certificate Information: 20330 W WINDSOR LANE 91326
- Application / Permit
- 20047-20000-01927
- Plan Check / Job No.
- B20VN14092
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW IRR SHAPED 33'X26' SWIMMING POOL AND SPA PER CITY STD PLAN #268 W/ SUPPL ENGR DETAIL.
- Permit Issued
- Issued on 12/11/2020
- Issuing Office
- Current Status
- CofO Issued on 8/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/6/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 11/9/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 12/1/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/11/2020 | JEROME MAGAT PALMA |
| Issued | 12/11/2020 | APPLICANT |
| CofO in Progress | 8/25/2021 | DAVID SCANTLIN |
| Permit Finaled | 8/25/2021 | JOHN JANSON |
| CofO Issued | 8/25/2021 | JOHN JANSON |
| Permit Finaled | 8/25/2021 | JOHN JANSON |
Permit Application Clearance Information
| Miscellaneous | Cleared | 12/8/2020 | DANG NGUYEN |
| Miscellaneous | Cleared | 12/8/2020 | DANG NGUYEN |
| ZA Case | Cleared | 12/8/2020 | DANG NGUYEN |
| ZA Case | Cleared | 12/8/2020 | DANG NGUYEN |
Contact Information
| Contractor | Green Scene The; Lic. No.: 340258-C53 | 21220 DEVONSHIRE ST STE 102 CHATSWORTH, CA 91311 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/16/2020 | Approved | DAVID SCANTLIN |
| Deputy Shotcrete | 12/18/2020 | Partial Approval | DAVID SCANTLIN |
| Grounding or Bonding | 3/9/2021 | Approved | DAVID SCANTLIN |
| Enclosure/Fence | 6/29/2021 | Approved | SEAN WIRCH |
| Pool Equipment Noise Test | 7/9/2021 | Corrections Issued | ROBERT GOLD |
| Equipment Noise Level | 7/22/2021 | Approved | ALFREDO FLORES |
| Pool Equipment Noise Test | 7/22/2021 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 8/16/2021 | Approved | DAVID SCANTLIN |
| Final | 8/16/2021 | Corrections Issued | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 8/16/2021 | SGSOV Approved | DAVID SCANTLIN |
| Final | 8/24/2021 | OK to Issue CofO | DAVID SCANTLIN |