17251 W KALISHER ST 91344

Certificate Information: 17251 W KALISHER ST 91344

Application / Permit
20047-20000-01918
Plan Check / Job No.
B20VN14065
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW IRREGULAR SHAPE 22'-3" X 31'-0" POOL AND 7' X 7' SPA PER CITY STANDARD PLAN # 268 AND DETAIL # 272-100.
Permit Issued
Issued on 8/3/2021
Issuing Office
Current Status
CofO Issued on 9/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2020 APPLICANT
Assigned to Plan Check Engineer 11/5/2020 PARISA ZAHABI
Corrections Issued 11/5/2020 PARISA ZAHABI
Applicant returned to address corrections 3/17/2021 PARISA ZAHABI
Plan Check Approved 7/21/2021 PARISA ZAHABI
Building Plans Picked Up 7/22/2021 APPLICANT
Issued 8/3/2021 APPLICANT
CofO in Progress 3/8/2022 DAVID SCANTLIN
CofO Issued 9/7/2022 DANIEL ORRANTE
Permit Finaled 9/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Construction near power lines Cleared 3/17/2021 OSCAR CASTRO
Grading Pre-Inspection Cleared 3/17/2021 PARISA ZAHABI
Eng Process Fee Ord 176,300 Cleared 4/8/2021 GABRIEL ROBLES
Work Adjacent to Public Way Cleared 6/16/2021 GABRIEL ROBLES

Contact Information

Contractor Dynamic Construction Pools & Spas; Lic. No.: 652598-C53 12522 BRADLEY AVENUE      SYLMAR, CA 91342

Inspector Information

JEFFREY PARD, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN BACK, (818) 774-4312 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 8/24/2021 Approved DAVID SCANTLIN
Deputy Shotcrete 8/30/2021 Approved DEANDRE HOFFMAN
Deputy Shotcrete 8/30/2021 Partial Approval DAVID SCANTLIN
Deck 11/9/2021 Approved DAVID SCANTLIN
Grounding or Bonding 11/9/2021 Approved DAVID SCANTLIN
Enclosure/Fence 11/23/2021 Not Ready for Inspection DAVID SCANTLIN
Enclosure/Fence 12/7/2021 Approved DAVID SCANTLIN
Equipment Noise Level 12/22/2021 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 1/10/2022 Approved SEAN HAUPT
Final 1/10/2022 Corrections Issued SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 1/10/2022 SGSOV Approved SEAN HAUPT
Final 3/7/2022 OK to Issue CofO DAVID SCANTLIN