3658 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3658 S MOUNTAIN VIEW AVE 90066

Application / Permit
20047-20000-01908
Plan Check / Job No.
B20VN14035
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED 17' X 43' POOL W/ 6' X 6' SPA W/ AUTOMATIC POOL COVER PER STANDARD PLAN #268 & ENGINEERING DETAILS.
Permit Issued
Issued on 1/26/2021
Issuing Office
Current Status
CofO Issued on 7/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/27/2020 APPLICANT
Assigned to Plan Check Engineer 11/4/2020 RAPHAEL ROSAS
Corrections Issued 11/6/2020 RAPHAEL ROSAS
Applicant returned to address corrections 12/21/2020 RAPHAEL ROSAS
Applicant returned to address corrections 1/5/2021 RAPHAEL ROSAS
Issued 1/26/2021 APPLICANT
CofO in Progress 7/7/2022 JOHNNY MIRANDA
Permit Finaled 7/7/2022 DANIEL ORRANTE
CofO Issued 7/7/2022 DANIEL ORRANTE
Permit Finaled 7/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Tract Map conditions Cleared 11/20/2020 TERRI OSBORNE
Work Adjacent to Public Way Cleared 12/11/2020 SAUL GARCIA
Grading Pre-Inspection Cleared 12/21/2020 RAPHAEL ROSAS
Eng Process Fee Ord 176,300 Cleared 1/22/2021 NIKTA MOUSAVI

Contact Information

Contractor Decardo'S Pools And Landscape Inc; Lic. No.: 532429-C53 23705 VANOWEN ST #114      WEST HILLS, CA 91307
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/8/2021 Approved OGANES TARAKHCHYAN
Pre-Gunite 6/8/2021 Approved OGANES TARAKHCHYAN
Deputy Shotcrete 6/14/2021 Partial Approval OGANES TARAKHCHYAN
Deck 9/2/2021 Approved OGANES TARAKHCHYAN
Enclosure/Fence 9/2/2021 Approved OGANES TARAKHCHYAN
Final 5/25/2022 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/25/2022 SGSOV Approved JOHNNY MIRANDA
Final 7/6/2022 OK to Issue CofO JOHNNY MIRANDA