927 W MARCO PL 90291

Certificate Information: 927 W MARCO PL 90291

Application / Permit
20047-20000-01883
Plan Check / Job No.
B20VN13903
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 8' X 28' POOL W/ 6' X 6' SPA PER STANDARD PLAN #268
Permit Issued
Issued on 6/30/2021
Issuing Office
Current Status
CofO Issued on 7/18/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2020 APPLICANT
Assigned to Plan Check Engineer 10/30/2020 RAPHAEL ROSAS
Corrections Issued 10/31/2020 RAPHAEL ROSAS
Applicant returned to address corrections 2/23/2021 RAPHAEL ROSAS
Issued 6/30/2021 APPLICANT
Building Plans Picked Up 7/1/2021 APPLICANT
CofO in Progress 7/12/2022 DAVID FEILER
Permit Finaled 7/18/2022 DANIEL ORRANTE
CofO Issued 7/18/2022 DANIEL ORRANTE
Permit Finaled 7/18/2022 DANIEL ORRANTE

Permit Application Clearance Information

Miscellaneous Cleared 2/16/2021 LAUREN PADICK
Miscellaneous Cleared 2/16/2021 LAUREN PADICK
Miscellaneous Cleared 2/16/2021 LAUREN PADICK
Specific Plan Cleared 2/16/2021 LAUREN PADICK
ZI Cleared 2/16/2021 LAUREN PADICK
ZI Cleared 2/18/2021 MELISSA JONES
Coastal Zone Cleared 6/21/2021 PABLO ESTRADA

Contact Information

Contractor J A B S Pools And Spas; Lic. No.: 936142-C53 8055 MATILIJA AVENUE      PANORAMA CITY, CA 91402
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 7/2/2021 Approved JOHNNY MIRANDA
Deck 10/12/2021 Approved JOHNNY MIRANDA
Rough-Electrical 10/12/2021 Approved JOHNNY MIRANDA
Rough-Plumbing 10/12/2021 Approved JOHNNY MIRANDA
Enclosure/Fence 1/13/2022 Corrections Issued DAVID FEILER
Enclosure/Fence 1/14/2022 Approved DAVID FEILER
Special/Order Compliance 1/14/2022 Partial Inspection DAVID FEILER
Pool Equipment Noise Test 2/11/2022 Approved JAMES VORHIS
Excavation/Setback/Form/Re-Bar 2/23/2022 Approved RICHARD STEINBACH
Final 2/23/2022 Corrections Issued RICHARD STEINBACH
SGSOV-Seismic Gas S/O Valve 2/23/2022 SGSOV Not Ready RICHARD STEINBACH
Final 6/8/2022 Conditional Approval JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 6/8/2022 SGSOV Approved JESUS RODRIGUEZ
Final 7/12/2022 OK to Issue CofO DAVID FEILER