2175 N MANDEVILLE CANYON ROAD 90049
Certificate Information: 2175 N MANDEVILLE CANYON ROAD 90049
- Application / Permit
- 20047-20000-01840
- Plan Check / Job No.
- B20VN13650
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- (N) POOL (35' X 15') & SPA (9' X 9') PER LA CITY STD PLAN #265, POOL/SPA COVER & ENG'R DETAILS
- Permit Issued
- Issued on 3/3/2021
- Issuing Office
- Current Status
- CofO Issued on 6/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/20/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 11/12/2020 | NILOOFAR MEHRAIN |
| Corrections Issued | 11/17/2020 | NILOOFAR MEHRAIN |
| Quality Review Completed | 11/17/2020 | CHON CHIO KUO |
| Applicant returned to address corrections | 12/15/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 1/15/2021 | NILOOFAR MEHRAIN |
| Issued | 3/3/2021 | APPLICANT |
| Building Plans Picked Up | 3/5/2021 | APPLICANT |
| CofO in Progress | 5/26/2026 | KEVIN SARGSYAN |
| Permit Finaled | 6/8/2026 | RICHARD STEINBACH |
| CofO Issued | 6/8/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/8/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| ZA Case | Cleared | 12/9/2020 | LAUREN PADICK |
| Grading Pre-Inspection | Cleared | 12/15/2020 | NILOOFAR MEHRAIN |
| Miscellaneous | Cleared | 12/22/2020 | MARC WOERSCHING |
| Miscellaneous | Cleared | 12/30/2020 | MARC WOERSCHING |
| Private street | Cleared | 1/11/2021 | MARC WOERSCHING |
Contact Information
| Contractor | Ahern Construction Corporation; Lic. No.: 687780-B | 3835-R THOUSAND OAKS BLVD #118 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Zhang,, Yao; Lic. No.: C74572 | 538 ROCCO CIRCLE CORONA, CA 92882 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Proofing Certificate | 3/22/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Pre-Gunite | 3/22/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Gunite | 3/24/2021 | Corrections Issued | MATT KELLERMAN |
| FLOOD-Proofing Certificate | 3/26/2021 | Approved | MATT KELLERMAN |
| Pre-Gunite | 3/26/2021 | Approved | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 6/28/2021 | Corrections Issued | CARLOS MATAMOROS |
| FLOOD-Elevation Certificate | 6/28/2021 | Not Ready for Inspection | CARLOS MATAMOROS |
| Grounding or Bonding | 3/9/2022 | Corrections Issued | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 4/10/2025 | Corrections Issued | KEVIN SARGSYAN |
| FLOOD-Elevation Certificate | 4/10/2025 | Approved | KEVIN SARGSYAN |
| Final | 4/10/2025 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2025 | SGSOV Not Ready | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 4/15/2025 | Approved | EUSEBIO GUZMAN |
| Excavation/Setback/Form/Re-Bar | 5/13/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| Final | 5/13/2026 | Not Ready for Inspection | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/13/2026 | SGSOV Not Ready | KEVIN SARGSYAN |
| Excavation/Setback/Form/Re-Bar | 5/26/2026 | Approved | KEVIN SARGSYAN |
| Final | 5/26/2026 | OK to Issue CofO | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 5/26/2026 | SGSOV Approved | KEVIN SARGSYAN |