1488 N RISING GLEN ROAD 90069
Certificate Information: 1488 N RISING GLEN ROAD 90069
- Application / Permit
- 20047-20000-01817
- Plan Check / Job No.
- B20VN13530
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- PROPOSED NEW 28'X15' NEW SWIMMING POOL W/ 7'X7' SPA PER CITY STD PLAN #268 & SUPPL ENGR DETAILS. SEE COMMENTS
- Permit Issued
- Issued on 12/23/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2020 | HAYATO TSUCHIYA |
| Corrections Issued | 10/30/2020 | HAYATO TSUCHIYA |
| Applicant returned to address corrections | 11/19/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 12/9/2020 | HAYATO TSUCHIYA |
| Issued | 12/23/2020 | APPLICANT |
| CofO in Progress | 8/12/2021 | RAUL BARAJAS |
| Permit Finaled | 8/13/2021 | DEROLD HAUFF |
| CofO Issued | 8/13/2021 | DEROLD HAUFF |
| Permit Finaled | 8/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Jr Pool & Spa Services; Lic. No.: 771197-C53 | P O BOX 5249 NORTH HOLLYWOOD, CA 91616 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/30/2020 | Approved | RAUL BARAJAS |
| Deputy Shotcrete | 1/7/2021 | No Access for Inspection | ELMER BLAND |
| Gas Piping or Gas Test | 3/8/2021 | Approved | RAUL BARAJAS |
| Grounding or Bonding | 3/8/2021 | Approved | RAUL BARAJAS |
| Enclosure/Fence | 4/28/2021 | Corrections Issued | RAUL BARAJAS |
| Enclosure/Fence | 5/10/2021 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 5/27/2021 | Approved | RAUL BARAJAS |
| Final | 5/27/2021 | Corrections Issued | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 5/27/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Enclosure/Fence | 6/7/2021 | Approved | RAUL BARAJAS |
| Final | 6/7/2021 | Conditional Approval | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Approved | RAUL BARAJAS |
| Final | 8/3/2021 | Corrections Issued | RAUL BARAJAS |
| Final | 8/6/2021 | Corrections Issued | RAUL BARAJAS |
| Final | 8/12/2021 | OK to Issue CofO | RAUL BARAJAS |