14903 W GREENLEAF ST 91403
Certificate Information: 14903 W GREENLEAF ST 91403
- Application / Permit
- 20047-20000-01805
- Plan Check / Job No.
- B20VN13474
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 34' X 18' SWIMMING POOL WITH 8' X 6' SPA PER STANDARD PLAN #268. AUTO POOL COVER PER ENGINEER DETAIL.
- Permit Issued
- Issued on 11/20/2020
- Issuing Office
- Current Status
- CofO Issued on 10/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2020 | ROSENDO MEDINA |
| Corrections Issued | 10/30/2020 | ROSENDO MEDINA |
| Plan Check Approved | 11/20/2020 | ROSENDO MEDINA |
| Issued | 11/20/2020 | APPLICANT |
| CofO in Progress | 10/3/2024 | JUAN VALENZUELA |
| Permit Finaled | 10/30/2024 | DANIEL ORRANTE |
| CofO Issued | 10/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 10/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/1/2020 | ROSENDO MEDINA |
Contact Information
| Contractor | Athlon Pool Company Inc; Lic. No.: 970093-C53 | 150 S GLENOAKS BLVD #9152 BURBANK, CA 91502 |
| Engineer | Biedenbach,, Christopher James; Lic. No.: C74003 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grounding or Bonding | 12/17/2020 | Approved | CHARLES POWELL |
| Pool Piping | 12/17/2020 | Partial Approval | CHARLES POWELL |
| Pool Piping | 12/18/2020 | Approved | CHARLES POWELL |
| Pre-Gunite | 12/18/2020 | Approved | CHARLES POWELL |
| Deputy Shotcrete | 12/21/2020 | Conditional Approval | CHRISTOPHE COCHRAN |
| Gas Piping or Gas Test | 1/8/2021 | Approved | CHARLES POWELL |
| Rough-Electrical | 1/8/2021 | Approved | CHARLES POWELL |
| Deck | 1/26/2021 | Approved | CHARLES POWELL |
| Grounding or Bonding | 1/26/2021 | Approved | CHARLES POWELL |
| Enclosure/Fence | 2/17/2021 | Not Ready for Inspection | CHARLES POWELL |
| Enclosure/Fence | 2/25/2021 | Approved | CHARLES POWELL |
| Pool Equipment Noise Test | 3/12/2021 | Not Ready for Inspection | FELIPE PENICHE |
| Excavation/Setback/Form/Re-Bar | 3/15/2021 | Approved | CHARLES POWELL |
| Final | 3/15/2021 | Corrections Issued | CHARLES POWELL |
| SGSOV-Seismic Gas S/O Valve | 3/15/2021 | SGSOV Approved | CHARLES POWELL |
| Equipment Noise Level | 3/18/2021 | Approved | FELIPE PENICHE |
| Final | 10/3/2024 | OK to Issue CofO | JUAN VALENZUELA |