846 S GENESEE AVE 90036
Certificate Information: 846 S GENESEE AVE 90036
- Application / Permit
- 20047-20000-01769
- Plan Check / Job No.
- B20VN13319
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 19'-0" X 13'-0" IRREG SHAPED SWIMMING POOL PER STANDARD PLAN #268
- Permit Issued
- Issued on 12/3/2020
- Issuing Office
- Current Status
- CofO Issued on 7/2/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/15/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 10/16/2020 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 11/13/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 12/3/2020 | JEROME MAGAT PALMA |
| Issued | 12/3/2020 | APPLICANT |
| CofO in Progress | 6/14/2021 | JOSEPH MCGARRY |
| Permit Finaled | 7/2/2021 | DEROLD HAUFF |
| CofO Issued | 7/2/2021 | DEROLD HAUFF |
| Permit Finaled | 7/2/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| CPC | Cleared | 10/26/2020 | MIGUEL GAMBOA |
| HPOZ | Cleared | 10/26/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | California Pools; Lic. No.: 185102-C53 | 901 CALLE AMANECER #115 SAN CLEMENTE, CA 92673 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 2/23/2021 | Approved | SCOTT FINNILA |
| Deputy Shotcrete | 2/24/2021 | Partial Approval | SCOTT FINNILA |
| Gas Piping or Gas Test | 3/22/2021 | Approved | CHRIS CHRISTENSEN |
| Gas Piping or Gas Test | 3/22/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Rough-Electrical | 3/22/2021 | Approved | CHRIS CHRISTENSEN |
| Deck | 4/20/2021 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 5/3/2021 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 5/25/2021 | Approved | JOSEPH MCGARRY |
| Final | 5/25/2021 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 5/25/2021 | SGSOV Approved | JOSEPH MCGARRY |
| Final | 6/10/2021 | OK to Issue CofO | JOSEPH MCGARRY |