7824 N KENTLAND AVE 91304

Certificate Information: 7824 N KENTLAND AVE 91304

Application / Permit
20047-20000-01751
Plan Check / Job No.
B20VN13209
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 18' X 34' POOL W/ 8' X 10' SPA WITHIN POOL SHELL PER LA CITY STANDARD PLAN #268
Permit Issued
Issued on 11/10/2020
Issuing Office
Current Status
CofO Issued on 6/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2020 APPLICANT
Assigned to Plan Check Engineer 10/28/2020 JENNIFER LEE
Corrections Issued 10/29/2020 JENNIFER LEE
Plan Check Approved 11/10/2020 JENNIFER LEE
Issued 11/10/2020 APPLICANT
CofO in Progress 6/10/2021 DAVID STEPANYAN
Permit Finaled 6/21/2021 JOHN JANSON
CofO Issued 6/21/2021 JOHN JANSON
Permit Finaled 6/21/2021 JOHN JANSON

Permit Application Clearance Information

Construction near power lines Cleared 11/2/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/11/2020 Corrections Issued DAVID STEPANYAN
Gas Piping or Gas Test 12/11/2020 Approved DAVID STEPANYAN
Pre-Gunite 12/11/2020 Not Ready for Inspection DAVID STEPANYAN
Deputy Shotcrete 4/20/2021 Corrections Issued DAVID STEPANYAN
Grounding or Bonding 4/20/2021 Partial Approval DAVID STEPANYAN
Enclosure/Fence 5/7/2021 Corrections Issued DAVID STEPANYAN
Enclosure/Fence 5/14/2021 Approved DAVID STEPANYAN
ELECTRICAL-Final 5/27/2021 Corrections Issued DAVID STEPANYAN
Excavation/Setback/Form/Re-Bar 5/27/2021 Approved DAVID STEPANYAN
Final 5/27/2021 Corrections Issued DAVID STEPANYAN
Pool Equipment Noise Test 5/27/2021 Approved ALFREDO FLORES
Pre-Gunite 5/27/2021 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 5/27/2021 SGSOV Approved DAVID STEPANYAN
Pre-Inspection 6/2/2021 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Final 6/9/2021 Approved DAVID STEPANYAN
Final 6/9/2021 OK to Issue CofO DAVID STEPANYAN