19939 W WELLS DR 91364

Certificate Information: 19939 W WELLS DR 91364

Application / Permit
20047-20000-01743
Plan Check / Job No.
B20VN13184
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 12' X 32' POOL W/ 6' X 6' SPA INSIDE PER STANDARD PLAN #270
Permit Issued
Issued on 10/29/2020
Issuing Office
Current Status
CofO Issued on 4/26/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2020 APPLICANT
Assigned to Plan Check Engineer 10/13/2020 RAPHAEL ROSAS
Corrections Issued 10/14/2020 RAPHAEL ROSAS
Issued 10/29/2020 APPLICANT
CofO in Progress 4/26/2021 DAVID SANDOVAL
Permit Finaled 4/26/2021 MICHAEL SMITH
CofO Issued 4/26/2021 MICHAEL SMITH
Permit Finaled 4/26/2021 MICHAEL SMITH

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/29/2020 RAPHAEL ROSAS

Contact Information

Contractor Noga Pool And Spa Inc; Lic. No.: 946647-C53 5739 KANAN ROAD #639      AGOURA HILLS, CA 91301
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 11/18/2020 No Access for Inspection DONALD SUNSERI
Pre-Gunite 11/24/2020 Corrections Issued DAVID SANDOVAL
Pre-Gunite 12/7/2020 Not Ready for Inspection VINCENT HANLEY
Pre-Gunite 12/9/2020 Conditional Approval DAVID SANDOVAL
Gas Piping or Gas Test 12/16/2020 Approved VINCENT HANLEY
Deck 3/15/2021 Approved DAVID SANDOVAL
Enclosure/Fence 3/15/2021 Approved DAVID SANDOVAL
Pool Equipment Noise Test 3/25/2021 Approved ALFREDO FLORES
Excavation/Setback/Form/Re-Bar 3/26/2021 No Access for Inspection DAVID SANDOVAL
Final 3/26/2021 No Access for Inspection DAVID SANDOVAL
Pre-Gunite 3/26/2021 Approved DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 3/26/2021 SGSOV Not Ready DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 4/26/2021 Approved DAVID SANDOVAL
Final 4/26/2021 OK to Issue CofO DAVID SANDOVAL
SGSOV-Seismic Gas S/O Valve 4/26/2021 SGSOV Approved DAVID SANDOVAL