4330 W PARVA AVE 90027
Certificate Information: 4330 W PARVA AVE 90027
- Application / Permit
- 20047-20000-01717
- Plan Check / Job No.
- B20VN13060
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 27' X 11'-6" SWIMMING POOL WITH 9'-6" X 11'-6" SPA PER STANDARD PLAN #268 AND ENGINEER DETAIL.
- Permit Issued
- Issued on 12/4/2020
- Issuing Office
- Current Status
- CofO Issued on 4/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/6/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | ROSENDO MEDINA |
| Corrections Issued | 10/11/2020 | ROSENDO MEDINA |
| Plan Check Approved | 12/3/2020 | ROSENDO MEDINA |
| Issued | 12/4/2020 | APPLICANT |
| CofO in Progress | 4/7/2021 | JOSEPH MCGARRY |
| Permit Finaled | 4/15/2021 | DEROLD HAUFF |
| CofO Issued | 4/15/2021 | DEROLD HAUFF |
| Permit Finaled | 4/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/12/2020 | ROSENDO MEDINA |
Contact Information
| Contractor | Aiden Pools; Lic. No.: 1053685-C53 | 1276 E COLORADO BLVD PASADENA, CA 91106 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/7/2021 | Approved | JOSEPH MCGARRY |
| Gas Piping or Gas Test | 1/7/2021 | Approved | JOSEPH MCGARRY |
| Grounding or Bonding | 1/7/2021 | Approved | JOSEPH MCGARRY |
| Pool Piping | 1/7/2021 | Approved | JOSEPH MCGARRY |
| Pre-Gunite | 1/7/2021 | Conditional Approval | JOSEPH MCGARRY |
| Deck | 1/20/2021 | Conditional Approval | JOSEPH MCGARRY |
| Deck | 2/5/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Deck | 2/17/2021 | Conditional Approval | JOSEPH MCGARRY |
| Enclosure/Fence | 3/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Enclosure/Fence | 3/17/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Deck | 3/19/2021 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 3/19/2021 | Approved | JOSEPH MCGARRY |
| Enclosure/Fence | 3/23/2021 | Approved | JOSEPH MCGARRY |
| Pool Equipment Noise Test | 3/26/2021 | Approved | ROBERT CHAVEZ |
| Final | 4/1/2021 | OK to Issue CofO | JOSEPH MCGARRY |
| Pre-Gunite | 4/1/2021 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 4/1/2021 | SGSOV Approved | JOSEPH MCGARRY |