23356 W BURTON ST 91304
Certificate Information: 23356 W BURTON ST 91304
- Application / Permit
- 20047-20000-01712
- Plan Check / Job No.
- B20VN13033
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 17'-0" X 32'-0" SWIMMING POOL AND 7'-0" X 7'-0" SPA WITHIN PER STANDARD PLAN #268
- Permit Issued
- Issued on 11/23/2020
- Issuing Office
- Current Status
- CofO Issued on 7/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/11/2020 | JEROME MAGAT PALMA |
| Issued | 11/23/2020 | APPLICANT |
| CofO in Progress | 7/3/2021 | DAVID STEPANYAN |
| CofO Issued | 7/8/2021 | JOHN JANSON |
| Permit Finaled | 7/8/2021 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/11/2020 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/14/2020 | Corrections Issued | DONALD SUNSERI |
| Excavation/Setback/Form/Re-Bar | 12/21/2020 | Approved | DAVID STEPANYAN |
| Gas Piping or Gas Test | 12/21/2020 | Approved | DAVID STEPANYAN |
| Grounding or Bonding | 12/21/2020 | Partial Approval | DAVID STEPANYAN |
| Pool Piping | 12/21/2020 | Approved | DAVID STEPANYAN |
| Pre-Gunite | 12/21/2020 | Approved | DAVID STEPANYAN |
| Deputy Shotcrete | 12/22/2020 | Conditional Approval | DAVID STEPANYAN |
| Deck | 1/19/2021 | Approved | TROY SANDERS |
| Enclosure/Fence | 2/8/2021 | Corrections Issued | DAVID STEPANYAN |
| Enclosure/Fence | 6/8/2021 | Approved | DAVID STEPANYAN |
| Pool Piping | 6/8/2021 | Approved | DAVID STEPANYAN |
| ELECTRICAL-Final | 6/23/2021 | Approved | DAVID STEPANYAN |
| Equipment Noise Level | 6/23/2021 | Not Ready for Inspection | FELIPE PENICHE |
| PLUMBING-Final | 6/23/2021 | Corrections Issued | DAVID STEPANYAN |
| Pool/Spa Cover | 6/23/2021 | Corrections Issued | DAVID STEPANYAN |
| PLUMBING-Final | 6/29/2021 | Not Ready for Inspection | DAVID STEPANYAN |
| Pool Equipment Noise Test | 6/29/2021 | Approved | ALFREDO FLORES |
| Pool/Spa Cover | 6/29/2021 | Approved | DAVID STEPANYAN |
| Final | 7/2/2021 | OK to Issue CofO | DAVID STEPANYAN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Approved | DAVID STEPANYAN |