10955 N LEOLANG AVE 91040
Certificate Information: 10955 N LEOLANG AVE 91040
- Application / Permit
- 20047-20000-01702
- Plan Check / Job No.
- B20VN12944
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 21'-0" X 20'-0" SWIMMING POOL AND 12'-10" DIAMETER SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 12/28/2020
- Issuing Office
- Current Status
- CofO Issued on 8/7/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/9/2020 | JEROME MAGAT PALMA |
| Corrections Issued | 10/11/2020 | JEROME MAGAT PALMA |
| Plan Check Approved | 10/28/2020 | JEROME MAGAT PALMA |
| Issued | 12/28/2020 | APPLICANT |
| CofO in Progress | 4/29/2021 | MATTHEW NELSON |
| Permit Finaled | 8/7/2021 | MICHAEL SMITH |
| CofO Issued | 8/7/2021 | MICHAEL SMITH |
| Permit Finaled | 8/7/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/11/2020 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 1/4/2021 | Partial Inspection | MATTHEW NELSON |
| Grounding or Bonding | 2/9/2021 | Approved | MATTHEW NELSON |
| Enclosure/Fence | 3/10/2021 | Corrections Issued | DONALD CRICHLOW |
| Enclosure/Fence | 3/16/2021 | Approved | MATTHEW NELSON |
| Pool Equipment Noise Test | 4/1/2021 | Not Ready for Inspection | FELIPE PENICHE |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Not Ready | MATTHEW NELSON |
| Pool Equipment Noise Test | 4/9/2021 | Approved | ALFREDO FLORES |
| Excavation/Setback/Form/Re-Bar | 4/13/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 4/13/2021 | Not Ready for Inspection | JOHN HAYES |
| Pre-Gunite | 4/13/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 4/13/2021 | SGSOV Not Ready | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 4/21/2021 | Approved | MATTHEW NELSON |
| Final | 4/21/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Pre-Gunite | 4/21/2021 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 4/21/2021 | SGSOV Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 4/28/2021 | Approved | MATTHEW NELSON |
| Final | 4/28/2021 | Not Ready for Inspection | MATTHEW NELSON |
| Final | 4/29/2021 | OK to Issue CofO | MATTHEW NELSON |