10338 W KESWICK AVE 90064

Certificate Information: 10338 W KESWICK AVE 90064

Application / Permit
20047-20000-01699
Plan Check / Job No.
B20VN12922
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 14' X 36' SWIMMING POOL AND 5'-6" X 9'-0" SPA WITHIN PER STANDARD PLAN #270
Permit Issued
Issued on 10/28/2020
Issuing Office
Current Status
CofO Issued on 3/15/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2020 APPLICANT
Assigned to Plan Check Engineer 10/9/2020 JEROME MAGAT PALMA
Corrections Issued 10/11/2020 JEROME MAGAT PALMA
Plan Check Approved 10/28/2020 JEROME MAGAT PALMA
Issued 10/28/2020 APPLICANT
CofO in Progress 2/12/2021 GERMAN RODRIGUEZ MENDOZA
CofO Issued 3/15/2021 VINCENT COTTON
Permit Finaled 3/15/2021 VINCENT COTTON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 10/11/2020 JEROME MAGAT PALMA
Construction near power lines Cleared 10/20/2020 WALTER RAMIREZ

Contact Information

Contractor Noga Pool And Spa Inc; Lic. No.: 946647-C53 5739 KANAN ROAD #639      AGOURA HILLS, CA 91301
Engineer Cordova,, Paul Phillip; Lic. No.: C72033 342 ROLLING HILLS AVE      SAN MATEO, CA 94403

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 11/13/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Pool Piping 11/13/2020 Approved GERMAN RODRIGUEZ MENDOZA
Pre-Gunite 11/13/2020 Approved GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 12/1/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deck 12/2/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 12/2/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 12/2/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Grounding or Bonding 12/4/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deck 12/9/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 12/9/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 12/15/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 12/16/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Enclosure/Fence 12/17/2020 Approved MATT KELLERMAN
Excavation/Setback/Form/Re-Bar 1/20/2021 Approved CHRISTOPHER WILSON
Final 1/20/2021 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 1/20/2021 SGSOV Approved CHRISTOPHER WILSON
Equipment Noise Level 1/21/2021 Approved ROBERT CHAVEZ
Final 1/27/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Final 2/5/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Final 2/9/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA