23923 W CROSSON DR 91367
Certificate Information: 23923 W CROSSON DR 91367
- Application / Permit
- 20047-20000-01685
- Plan Check / Job No.
- B20VN12833
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 16' X 32' POOL WITH 7' X 7' SPA INSIDE PER STANDARD PLAN #268
- Permit Issued
- Issued on 10/26/2020
- Issuing Office
- Current Status
- CofO Issued on 5/14/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2020 | RAPHAEL ROSAS |
| Corrections Issued | 10/9/2020 | RAPHAEL ROSAS |
| Issued | 10/26/2020 | APPLICANT |
| CofO in Progress | 5/12/2021 | TROY SANDERS |
| Permit Finaled | 5/14/2021 | JOHN JANSON |
| CofO Issued | 5/14/2021 | JOHN JANSON |
| Permit Finaled | 5/14/2021 | JOHN JANSON |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/23/2020 | RAPHAEL ROSAS |
Contact Information
| Contractor | Decardo'S Pools And Landscape Inc; Lic. No.: 532429-C53 | 23705 VANOWEN ST #114 WEST HILLS, CA 91307 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/7/2020 | Approved | TROY SANDERS |
| Gas Piping or Gas Test | 12/7/2020 | Approved | TROY SANDERS |
| Pool Piping | 12/7/2020 | Approved | TROY SANDERS |
| Pre-Gunite | 12/7/2020 | Approved | TROY SANDERS |
| Rough-Electrical | 12/7/2020 | Approved | TROY SANDERS |
| Deputy Shotcrete | 12/8/2020 | Approved | TROY SANDERS |
| Deck | 12/23/2020 | Approved | TROY SANDERS |
| Grounding or Bonding | 12/23/2020 | Approved | TROY SANDERS |
| Enclosure/Fence | 4/14/2021 | Approved | TROY SANDERS |
| Equipment Noise Level | 5/3/2021 | Approved | FELIPE PENICHE |
| Final | 5/4/2021 | Corrections Issued | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/4/2021 | SGSOV Approved | TROY SANDERS |
| Final | 5/12/2021 | OK to Issue CofO | TROY SANDERS |