9401 N VALJEAN AVE 91343

Certificate Information: 9401 N VALJEAN AVE 91343

Application / Permit
20047-20000-01595
Plan Check / Job No.
B20VN12429
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 12' X 30' POOL PER STANDARD PLAN #254
Permit Issued
Issued on 2/19/2021
Issuing Office
Current Status
CofO Issued on 1/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2020 APPLICANT
Assigned to Plan Check Engineer 10/2/2020 RAPHAEL ROSAS
Corrections Issued 10/5/2020 RAPHAEL ROSAS
Applicant returned to address corrections 1/25/2021 RAPHAEL ROSAS
Plan Check Approved 2/2/2021 RAPHAEL ROSAS
Issued 2/19/2021 APPLICANT
CofO in Progress 10/28/2021 RAUL OLAGI
CofO Issued 1/15/2022 MICHAEL SMITH
Permit Finaled 1/15/2022 MICHAEL SMITH

Permit Application Clearance Information

ZA Case Cleared 10/14/2020 MIGUEL GAMBOA
Grading Pre-Inspection Cleared 1/25/2021 RAPHAEL ROSAS
Construction near power lines Cleared 2/2/2021 JOHN BACON

Contact Information

Contractor Owner-Builder       ,
Engineer Azizisefat,, Solayman; Lic. No.: C57840 19510 VENTURA BLVD STE 110      TARZANA, CA 91356

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/9/2021 Approved ARTHUR SARGSYAN
Gas Piping or Gas Test 3/9/2021 Approved ARTHUR SARGSYAN
Pool Piping 3/9/2021 Approved ARTHUR SARGSYAN
Pre-Inspection 3/9/2021 Approved ARTHUR SARGSYAN
Rough-Electrical 3/9/2021 Approved ARTHUR SARGSYAN
Rough-Plumbing 3/9/2021 Approved ARTHUR SARGSYAN
Enclosure/Fence 4/8/2021 Approved ARTHUR SARGSYAN
Final 4/16/2021 Corrections Issued ARTHUR SARGSYAN
Pre-Gunite 4/16/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 4/16/2021 SGSOV Approved ARTHUR SARGSYAN
Equipment Noise Level 4/23/2021 Approved FELIPE PENICHE
Final 5/4/2021 No Access for Inspection ARTHUR SARGSYAN
Pre-Gunite 5/4/2021 No Access for Inspection ARTHUR SARGSYAN
Final 6/7/2021 Corrections Issued MICHAEL PELHAM
Pre-Gunite 6/7/2021 Approved MICHAEL PELHAM
Final 7/16/2021 Corrections Issued JACK KARGODORIAN
Grading Pre-Inspection 7/22/2021 Approved MANUEL TEJADA
Final 9/15/2021 Not Ready for Inspection JACK KARGODORIAN
Final 10/27/2021 OK to Issue CofO RAUL OLAGI