24617 W EILAT ST 91367

Certificate Information: 24617 W EILAT ST 91367

Application / Permit
20047-20000-01544
Plan Check / Job No.
B20VN12069
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 17' X 38' POOL W/ 7' X 7' SPA WITHIN POOL SHELL AND POOL COVER PER LA CITY STANDARD PLAN #268 AND DETAIL #: 320 AND 672
Permit Issued
Issued on 11/4/2020
Issuing Office
Current Status
CofO Issued on 3/18/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/11/2020 APPLICANT
Assigned to Plan Check Engineer 9/18/2020 JENNIFER LEE
Corrections Issued 9/21/2020 JENNIFER LEE
Plan Check Approved 11/2/2020 JENNIFER LEE
Issued 11/4/2020 APPLICANT
CofO in Progress 12/16/2022 TROY SANDERS
Permit Finaled 3/18/2023 DANIEL ORRANTE
CofO Issued 3/18/2023 DANIEL ORRANTE
Permit Finaled 3/18/2023 DANIEL ORRANTE

Permit Application Clearance Information

Grading Pre-Inspection Cleared 9/21/2020 JENNIFER LEE

Contact Information

Contractor Ultimate Water Creations Inc; Lic. No.: 702889-C53 2934 BEVERLY GLEN CIRCLE      BEL AIR, CA 90077
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 12/11/2020 Approved TROY SANDERS
Grounding or Bonding 12/11/2020 Approved TROY SANDERS
Pool Piping 12/11/2020 Approved TROY SANDERS
Pre-Gunite 12/11/2020 Approved TROY SANDERS
Rough-Electrical 12/11/2020 Approved TROY SANDERS
Rough-Plumbing 12/11/2020 Approved TROY SANDERS
Deputy Shotcrete 1/4/2021 Partial Approval TROY SANDERS
Deck 3/8/2021 Approved TROY SANDERS
Enclosure/Fence 6/7/2021 Approved PETER FOLLING
Excavation/Setback/Form/Re-Bar 10/5/2021 Approved TROY SANDERS
Final 10/5/2021 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 10/5/2021 SGSOV Not Ready TROY SANDERS
Final 6/22/2022 Not Ready for Inspection TROY SANDERS
SGSOV-Seismic Gas S/O Valve 6/22/2022 SGSOV Approved TROY SANDERS
Final 6/30/2022 Corrections Issued TROY SANDERS
Equipment Noise Level 12/9/2022 Approved ALFREDO FLORES
Final 12/15/2022 OK to Issue CofO TROY SANDERS