4985 N WAWONA ST 90041

Certificate Information: 4985 N WAWONA ST 90041

Application / Permit
20047-20000-01539
Plan Check / Job No.
B20VN12046
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 16 X 26 POOL WITH A 7' X 7' SPA INSIDE THE SHELL PER STD PLAN 268 AND DETAIL 320.
Permit Issued
Issued on 1/8/2021
Issuing Office
Current Status
CofO Issued on 9/8/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/13/2020 APPLICANT
Assigned to Plan Check Engineer 9/18/2020 PINANK PATEL
Corrections Issued 9/21/2020 PINANK PATEL
Plan Check Approved 1/8/2021 PINANK PATEL
Issued 1/8/2021 APPLICANT
CofO in Progress 9/2/2022 CRAIG VAUGHAN
Permit Finaled 9/8/2022 DEROLD HAUFF
CofO Issued 9/8/2022 DEROLD HAUFF
Permit Finaled 9/8/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/29/2020 CECILIO NAVARRO
Miscellaneous Cleared 12/14/2020 HOK CHI CHIU
Sewer availability Cleared 12/18/2020 CECILIO NAVARRO

Contact Information

Contractor Pool Logic La; Lic. No.: 1053685-C53 1276 E COLORADO BLVD      PASADENA, CA 91106
Engineer Lacher,, Todd Lee; Lic. No.: C67656 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Gunite 1/19/2021 Approved CRAIG VAUGHAN
Enclosure/Fence 3/3/2021 Corrections Issued CRAIG VAUGHAN
Deck 3/22/2021 Corrections Issued CRAIG VAUGHAN
Enclosure/Fence 3/22/2021 Corrections Issued CRAIG VAUGHAN
Deck 4/7/2021 Not Ready for Inspection BRIAN SULLIVAN
Enclosure/Fence 4/7/2021 Corrections Issued BRIAN SULLIVAN
Deck 4/16/2021 Partial Approval SCOTT FINNILA
Enclosure/Fence 4/16/2021 Approved SCOTT FINNILA
Pool Equipment Noise Test 5/19/2021 Approved ROBERT CHAVEZ
Excavation/Setback/Form/Re-Bar 6/17/2021 Approved CRAIG VAUGHAN
Final 6/17/2021 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 6/17/2021 SGSOV Not Ready CRAIG VAUGHAN
Final 9/1/2022 OK to Issue CofO CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 9/1/2022 SGSOV Approved CRAIG VAUGHAN