2101 S DUXBURY CIR 90034
Certificate Information: 2101 S DUXBURY CIR 90034
- Application / Permit
- 20047-20000-01535
- Plan Check / Job No.
- B20VN12036
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 30' X 15' SWIMMING POOL WITH 7' X 7' SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 10/28/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/3/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/11/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2020 | ROSENDO MEDINA |
| Corrections Issued | 9/16/2020 | ROSENDO MEDINA |
| Plan Check Approved | 10/14/2020 | ROSENDO MEDINA |
| Issued | 10/28/2020 | APPLICANT |
| CofO in Progress | 9/30/2021 | KEVIN SARGSYAN |
| Permit Finaled | 12/3/2021 | KENNETH NAGLE |
| CofO Issued | 12/3/2021 | KENNETH NAGLE |
| Permit Finaled | 12/3/2021 | KENNETH NAGLE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 9/16/2020 | ROSENDO MEDINA |
Contact Information
| Contractor | Jr Pool & Spa Services; Lic. No.: 771197-C53 | P O BOX 5249 NORTH HOLLYWOOD, CA 91616 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/9/2020 | Approved | KEVIN SARGSYAN |
| Pool Piping | 11/9/2020 | Approved | KEVIN SARGSYAN |
| Pre-Gunite | 11/9/2020 | Conditional Approval | KEVIN SARGSYAN |
| Gas Piping or Gas Test | 12/3/2020 | Approved | KEVIN SARGSYAN |
| Deck | 3/5/2021 | Approved | KEVIN SARGSYAN |
| Enclosure/Fence | 7/1/2021 | Approved | KEVIN SARGSYAN |
| Pool Equipment Noise Test | 9/17/2021 | Approved | ROBERT CHAVEZ |
| Final | 9/20/2021 | Corrections Issued | KEVIN SARGSYAN |
| Pre-Gunite | 9/20/2021 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 9/20/2021 | SGSOV Approved | KEVIN SARGSYAN |
| Final | 9/30/2021 | OK to Issue CofO | KEVIN SARGSYAN |