4961 N ODESSA AVE 91436
Certificate Information: 4961 N ODESSA AVE 91436
- Application / Permit
- 20047-20000-01523
- Plan Check / Job No.
- B20VN11926
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 29' X 20' POOL WITH A 8' X 9' ATTACHED SPA PER STD PLAN 268, AND DETAIL # 640 AND 551
- Permit Issued
- Issued on 12/15/2020
- Issuing Office
- Current Status
- CofO Issued on 6/5/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/13/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/18/2020 | PINANK PATEL |
| Corrections Issued | 9/21/2020 | PINANK PATEL |
| Plan Check Approved | 12/15/2020 | PINANK PATEL |
| Issued | 12/15/2020 | APPLICANT |
| CofO in Progress | 5/10/2021 | MICHAEL PELHAM |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
| CofO Issued | 6/5/2021 | MICHAEL SMITH |
| Permit Finaled | 6/5/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/30/2020 | RIDWAN HARDY |
| Construction within easement | Cleared | 11/30/2020 | RIDWAN HARDY |
Contact Information
| Contractor | Avanti Pools Inc; Lic. No.: 772516-C53 | 8138 ORION AVE VAN NUYS, CA 91406 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/18/2020 | Corrections Issued | MICHAEL TEMPLE |
| Gas Piping or Gas Test | 1/5/2021 | Not Ready for Inspection | DANIEL ORRANTE |
| Grounding or Bonding | 1/5/2021 | Approved | DANIEL ORRANTE |
| Pool Piping | 1/5/2021 | Approved | DANIEL ORRANTE |
| Pre-Gunite | 1/5/2021 | Corrections Issued | BRENDAN LOONEY |
| Pre-Inspection | 1/5/2021 | Partial Inspection | DANIEL ORRANTE |
| Rough-Electrical | 1/5/2021 | Not Ready for Inspection | DANIEL ORRANTE |
| Excavation/Setback/Form/Re-Bar | 5/10/2021 | Approved | MICHAEL PELHAM |
| Final | 5/10/2021 | OK to Issue CofO | MICHAEL PELHAM |
| Pre-Gunite | 5/10/2021 | Approved | MICHAEL PELHAM |
| SGSOV-Seismic Gas S/O Valve | 5/10/2021 | SGSOV Approved | MICHAEL PELHAM |