11709 N MCLENNAN AVE 91344
Certificate Information: 11709 N MCLENNAN AVE 91344
- Application / Permit
- 20047-20000-01465
- Plan Check / Job No.
- B20VN11698
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 27' POOL WITH A 5.5' X 7' SPA PER STANDARD PLAN #268.
- Permit Issued
- Issued on 9/22/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 8/23/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | CRISTINA SALAZAR |
| Corrections Issued | 9/11/2020 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 9/22/2020 | ALFRED RAMIREZ |
| Plan Check Approved | 9/22/2020 | ALFRED RAMIREZ |
| Issued | 9/22/2020 | APPLICANT |
| CofO in Progress | 1/15/2021 | MARK JOHNSON |
| No Progress | 1/30/2021 | MICHAEL TEMPLE |
| CofO in Progress | 7/26/2022 | MICHAEL TEMPLE |
| CofO Issued | 8/23/2022 | MICHAEL SMITH |
| Permit Finaled | 8/23/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Omega Construction Co Inc; Lic. No.: 464910-B | P O BOX 7038 NORTHRIDGE, CA 91327 |
| Engineer | Thompson,, Matthew Gregory; Lic. No.: C86051 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/16/2020 | Not Ready for Inspection | MARK JOHNSON |
| Gas Piping or Gas Test | 10/16/2020 | Not Ready for Inspection | MARK JOHNSON |
| Pool Piping | 10/16/2020 | Not Ready for Inspection | MARK JOHNSON |
| Rough-Electrical | 10/16/2020 | Not Ready for Inspection | MARK JOHNSON |
| Rough-Plumbing | 10/16/2020 | Not Ready for Inspection | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 10/26/2020 | Approved | MARK JOHNSON |
| Gas Piping or Gas Test | 10/26/2020 | Approved | MARK JOHNSON |
| Grounding or Bonding | 10/26/2020 | Approved | MARK JOHNSON |
| Pool Piping | 10/26/2020 | Approved | MARK JOHNSON |
| Rough-Electrical | 10/26/2020 | Approved | MARK JOHNSON |
| Rough-Plumbing | 10/26/2020 | Approved | MARK JOHNSON |
| Deck | 11/10/2020 | Approved | MARK JOHNSON |
| Grounding or Bonding | 11/10/2020 | Approved | MARK JOHNSON |
| Enclosure/Fence | 12/7/2020 | Approved | MARK JOHNSON |
| Final | 1/5/2021 | Corrections Issued | MARK JOHNSON |
| Pre-Gunite | 1/5/2021 | Approved | MARK JOHNSON |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Approved | MARK JOHNSON |
| Final | 1/14/2021 | OK to Issue CofO | MARK JOHNSON |
| Special/Order Compliance | 2/1/2021 | Corrections Issued | MARK JOHNSON |
| Equipment Noise Level | 2/2/2021 | Approved | ROBERT GOLD |