11709 N MCLENNAN AVE 91344

Certificate Information: 11709 N MCLENNAN AVE 91344

Application / Permit
20047-20000-01465
Plan Check / Job No.
B20VN11698
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
NEW 15' X 27' POOL WITH A 5.5' X 7' SPA PER STANDARD PLAN #268.
Permit Issued
Issued on 9/22/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/4/2020 APPLICANT
Assigned to Plan Check Engineer 9/10/2020 CRISTINA SALAZAR
Corrections Issued 9/11/2020 CRISTINA SALAZAR
Applicant returned to address corrections 9/22/2020 ALFRED RAMIREZ
Plan Check Approved 9/22/2020 ALFRED RAMIREZ
Issued 9/22/2020 APPLICANT
CofO in Progress 1/15/2021 MARK JOHNSON
No Progress 1/30/2021 MICHAEL TEMPLE
CofO in Progress 7/26/2022 MICHAEL TEMPLE
CofO Issued 8/23/2022 MICHAEL SMITH
Permit Finaled 8/23/2022 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Omega Construction Co Inc; Lic. No.: 464910-B P O BOX 7038      NORTHRIDGE, CA 91327
Engineer Thompson,, Matthew Gregory; Lic. No.: C86051 1201 N TUSTIN AVE      ANAHEIM, CA 92807

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/16/2020 Not Ready for Inspection MARK JOHNSON
Gas Piping or Gas Test 10/16/2020 Not Ready for Inspection MARK JOHNSON
Pool Piping 10/16/2020 Not Ready for Inspection MARK JOHNSON
Rough-Electrical 10/16/2020 Not Ready for Inspection MARK JOHNSON
Rough-Plumbing 10/16/2020 Not Ready for Inspection MARK JOHNSON
Excavation/Setback/Form/Re-Bar 10/26/2020 Approved MARK JOHNSON
Gas Piping or Gas Test 10/26/2020 Approved MARK JOHNSON
Grounding or Bonding 10/26/2020 Approved MARK JOHNSON
Pool Piping 10/26/2020 Approved MARK JOHNSON
Rough-Electrical 10/26/2020 Approved MARK JOHNSON
Rough-Plumbing 10/26/2020 Approved MARK JOHNSON
Deck 11/10/2020 Approved MARK JOHNSON
Grounding or Bonding 11/10/2020 Approved MARK JOHNSON
Enclosure/Fence 12/7/2020 Approved MARK JOHNSON
Final 1/5/2021 Corrections Issued MARK JOHNSON
Pre-Gunite 1/5/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 1/5/2021 SGSOV Approved MARK JOHNSON
Final 1/14/2021 OK to Issue CofO MARK JOHNSON
Special/Order Compliance 2/1/2021 Corrections Issued MARK JOHNSON
Equipment Noise Level 2/2/2021 Approved ROBERT GOLD