13640 1/2 N DRONFIELD AVE 91342
Certificate Information: 13640 1/2 N DRONFIELD AVE 91342
- Application / Permit
- 20047-20000-01406
- Plan Check / Job No.
- B20VN11347
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 15' X 25' POOL W/ 5'-6" X 7' SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 9/30/2020
- Issuing Office
- Current Status
- CofO Issued on 12/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2020 | RAPHAEL ROSAS |
| Corrections Issued | 9/22/2020 | RAPHAEL ROSAS |
| Issued | 9/30/2020 | APPLICANT |
| CofO in Progress | 5/26/2021 | MISAEL ESPARZA |
| CofO Issued | 12/17/2021 | MICHAEL SMITH |
| Permit Finaled | 12/17/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| "Q" conditions | Cleared | 9/24/2020 | MIGUEL GAMBOA |
| Tract Map conditions | Cleared | 9/24/2020 | MIGUEL GAMBOA |
| ZA Case | Cleared | 9/24/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | Premier Pool Plastering; Lic. No.: 625132-C53 | 14520 FOOTHILL BLVD SYLMAR, CA 91342 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Gas Piping or Gas Test | 10/21/2020 | Approved | MISAEL ESPARZA |
| Pre-Gunite | 10/21/2020 | Conditional Approval | MISAEL ESPARZA |
| Deputy Shotcrete | 10/28/2020 | No Result Entered | KENNETH KUROWSKI |
| Deck | 11/13/2020 | Approved | MISAEL ESPARZA |
| Enclosure/Fence | 12/22/2020 | Corrections Issued | MISAEL ESPARZA |
| Enclosure/Fence | 12/29/2020 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/10/2021 | SGSOV Not Ready | MISAEL ESPARZA |
| Pre-Inspection | 5/14/2021 | No Access for Inspection | MISAEL ESPARZA |
| Pool Equipment Noise Test | 5/21/2021 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 5/25/2021 | Approved | MISAEL ESPARZA |
| Excavation/Setback/Form/Re-Bar | 5/25/2021 | Approved | MISAEL ESPARZA |
| Final | 5/25/2021 | OK to Issue CofO | MISAEL ESPARZA |
| Pre-Gunite | 5/25/2021 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 5/25/2021 | SGSOV Approved | MISAEL ESPARZA |