10200 N NOBLE AVE 91345
Certificate Information: 10200 N NOBLE AVE 91345
- Application / Permit
- 20047-20000-01405
- Plan Check / Job No.
- B20VN11344
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW ( 17'-0"x 32'-0") POOL WITH (7'-0"x 7'-0") SPA PER LA CITY STANDARD PLAN #268.
- Permit Issued
- Issued on 11/23/2020
- Issuing Office
- Current Status
- CofO Issued on 7/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/4/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/10/2020 | FERNANDO FLORES |
| Corrections Issued | 9/10/2020 | FERNANDO FLORES |
| Plan Check Approved | 11/23/2020 | TROY DEGUZMAN |
| Issued | 11/23/2020 | APPLICANT |
| CofO in Progress | 5/27/2021 | JENNIFER RABUCHIN |
| Permit Finaled | 7/10/2021 | MICHAEL SMITH |
| CofO Issued | 7/10/2021 | MICHAEL SMITH |
| Permit Finaled | 7/10/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Premier Pool Plastering; Lic. No.: 625132-C35 | 14520 FOOTHILL BLVD SYLMAR, CA 91342 |
| Engineer | Lacher,, Todd Lee; Lic. No.: C67656 | 1201 N TUSTIN AVE ANAHEIM, CA 92807 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/8/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Gas Piping or Gas Test | 12/8/2020 | Conditional Approval | JENNIFER RABUCHIN |
| Grounding or Bonding | 12/8/2020 | Conditional Approval | JENNIFER RABUCHIN |
| Pool Piping | 12/8/2020 | Conditional Approval | JENNIFER RABUCHIN |
| Pre-Gunite | 12/8/2020 | Conditional Approval | JENNIFER RABUCHIN |
| Rough-Electrical | 12/8/2020 | Conditional Approval | JENNIFER RABUCHIN |
| Pre-Inspection | 12/15/2020 | Corrections Issued | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 3/25/2021 | Approved | MICHAEL TEMPLE |
| Pre-Gunite | 3/25/2021 | Approved | MICHAEL TEMPLE |
| Deck | 4/23/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Deck | 5/11/2021 | Approved | JENNIFER RABUCHIN |
| Enclosure/Fence | 5/11/2021 | Approved | JENNIFER RABUCHIN |
| Pool Equipment Noise Test | 5/25/2021 | Approved | FELIPE PENICHE |
| ELECTRICAL-Final | 5/27/2021 | Approved | JENNIFER RABUCHIN |
| Final | 5/27/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 5/27/2021 | SGSOV Approved | JENNIFER RABUCHIN |