13242 W SCHOENBORN ST 91352

Certificate Information: 13242 W SCHOENBORN ST 91352

Application / Permit
20047-20000-01371
Plan Check / Job No.
B20VN11120
Group
Building
Type
Swimming-Pool/Spa
Sub-Type
1 or 2 Family Dwelling
Primary Use
(20) Pool/Spa - Private
Work Description
PROPOSED NEW IRREGULAR 17' x 34' POOL AND 9' x 9' SPA PER CITY STD PLAN # 270.
Permit Issued
Issued on 1/4/2021
Issuing Office
Current Status
CofO Issued on 9/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/30/2020 APPLICANT
Assigned to Plan Check Engineer 9/9/2020 HAYATO TSUCHIYA
Corrections Issued 9/10/2020 HAYATO TSUCHIYA
Applicant returned to address corrections 10/2/2020 LUIS RINCON
Applicant returned to address corrections 10/26/2020 LUIS RINCON
Plan Check Approved 11/17/2020 LUIS RINCON
Issued 1/4/2021 APPLICANT
CofO in Progress 9/16/2021 GREGG CUMMINGS
Permit Finaled 9/17/2021 MICHAEL SMITH
CofO Issued 9/17/2021 MICHAEL SMITH
Permit Finaled 9/17/2021 MICHAEL SMITH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Cristescu,, Barbu D; Lic. No.: C72038 14401 SYLVAN STREET 209      VAN NUYS, CA 91401

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Piping or Gas Test 1/28/2021 No Access for Inspection GREGG CUMMINGS
Grounding or Bonding 1/28/2021 No Access for Inspection GREGG CUMMINGS
Pool Piping 1/28/2021 No Access for Inspection GREGG CUMMINGS
Pre-Inspection 1/28/2021 No Access for Inspection GREGG CUMMINGS
Rough-Electrical 1/28/2021 No Access for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 2/4/2021 Corrections Issued JENNIFER RABUCHIN
Gas Piping or Gas Test 2/4/2021 Partial Approval JENNIFER RABUCHIN
Grounding or Bonding 2/4/2021 Not Ready for Inspection JENNIFER RABUCHIN
Pool Piping 2/4/2021 Not Ready for Inspection JENNIFER RABUCHIN
Pre-Gunite 2/4/2021 Corrections Issued JENNIFER RABUCHIN
Pre-Gunite 4/16/2021 Not Ready for Inspection GREGG CUMMINGS
Pre-Gunite 4/26/2021 No Access for Inspection GREGG CUMMINGS
Pre-Gunite 5/4/2021 Approved GREGG CUMMINGS
Deck 6/2/2021 Approved GREGG CUMMINGS
Enclosure/Fence 8/12/2021 Corrections Issued GREGG CUMMINGS
Enclosure/Fence 8/16/2021 Approved GREGG CUMMINGS
Enclosure/Fence 8/17/2021 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Final 9/16/2021 Approved GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 9/16/2021 Approved GREGG CUMMINGS
Final 9/16/2021 OK to Issue CofO GREGG CUMMINGS
PLUMBING-Final 9/16/2021 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved GREGG CUMMINGS