480 N BUNDY DR 90049
Certificate Information: 480 N BUNDY DR 90049
- Application / Permit
- 20047-20000-01369
- Plan Check / Job No.
- B20VN11110
- Group
- Building
- Type
- Swimming-Pool/Spa
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (20) Pool/Spa - Private
- Work Description
- NEW 20' x 38' POOL WITH A 7'-6" x 11' SPA PER STANDARD PLAN #268
- Permit Issued
- Issued on 10/27/2020
- Issuing Office
- Current Status
- CofO Issued on 1/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/27/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 9/3/2020 | RICARDO RAMIREZ |
| Corrections Issued | 9/5/2020 | RICARDO RAMIREZ |
| Plan Check Approved | 9/30/2020 | ANGELICA MARTINEZ |
| Issued | 10/27/2020 | APPLICANT |
| CofO in Progress | 1/12/2024 | CARLOS MATAMOROS |
| Permit Finaled | 1/18/2024 | DANIEL ORRANTE |
| CofO Issued | 1/18/2024 | DANIEL ORRANTE |
| Permit Finaled | 1/18/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Gunite | 12/3/2020 | Corrections Issued | CARLOS MATAMOROS |
| Grounding or Bonding | 12/7/2020 | Approved | CARLOS MATAMOROS |
| Pool Piping | 12/7/2020 | Approved | CARLOS MATAMOROS |
| Pre-Gunite | 12/7/2020 | Approved | CARLOS MATAMOROS |
| Gas Piping or Gas Test | 2/17/2021 | Partial Approval | CARLOS MATAMOROS |
| Gunite | 7/8/2022 | Approved | CARLOS MATAMOROS |
| Rough-Plumbing | 7/8/2022 | Approved | CARLOS MATAMOROS |
| Deputy Shotcrete | 8/1/2022 | Conditional Approval | CLAYTON GRAHAM |
| Deck | 9/14/2022 | Approved | CARLOS MATAMOROS |
| Enclosure/Fence | 9/14/2022 | Approved | CARLOS MATAMOROS |
| Equipment Noise Level | 9/27/2022 | Approved | JUSTIN CURTIS |
| Final | 5/24/2023 | Corrections Issued | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/24/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 5/30/2023 | Approved | CARLOS MATAMOROS |
| Final | 5/30/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 5/30/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Final | 7/5/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 7/5/2023 | SGSOV Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 1/11/2024 | Approved | CARLOS MATAMOROS |
| Final | 1/11/2024 | OK to Issue CofO | CARLOS MATAMOROS |
| PLUMBING-Final | 1/11/2024 | Approved | CARLOS MATAMOROS |